Free RAMS Template Generator for Construction (2026)
Generate a job-specific RAMS (Risk Assessment & Method Statement) in 2 minutes. Built to a verified HSE standard, written for CDM 2015 sites, tailored to your exact construction activity. Not a generic template you fill in yourself.
What is a RAMS?
A RAMS is a combined Risk Assessment and Method Statement. It identifies the hazards associated with a construction activity, evaluates the risks using a likelihood x severity matrix, and describes the step-by-step safe working procedure with control measures.
Under the Construction (Design and Management) Regulations 2015 (CDM 2015) and the Management of Health and Safety at Work Regulations 1999, every construction activity requires a risk assessment. Principal contractors typically require a RAMS before any subcontractor begins work on site.
What a RAMS Should Contain
- Document control (version, date, author, reviewer)
- Project information (site, client, principal contractor, duration)
- Scope of works (description of activities)
- Hazard identification table with risk scores before and after controls
- Method statement (step-by-step safe working procedure)
- PPE requirements with BS EN standards
- Emergency procedures (first aid, fire, evacuation)
- Environmental considerations (noise, dust, waste)
- Welfare arrangements
- Signatures and acceptance section
Why Generic Templates Don't Work
Generic RAMS templates are one-size-fits-all. They don't account for your specific job, your site conditions, or your particular hazards.
A bricklayer laying blocks at ground level has completely different hazards to a roofer working at height. A plumber doing a bathroom refit faces different risks to an electrician rewiring a commercial kitchen. Your RAMS should reflect your actual work.
RAMSReady generates documents tailored to your exact job description, identifying the specific hazards and citing the exact regulations that apply to your work.
The five steps a risk assessment has to follow
HSE set out risk management as five steps, and a RAMS that skips one of them is the kind that comes back from a principal contractor:
- Identify the hazards. Look at how people actually work, how plant and equipment get used, what substances are on site, what unsafe practices have crept in, and the state of the premises. HSE are explicit that you should include non-routine work such as maintenance, cleaning and changes in the work cycle, and that past accident records are worth reading because they surface the hazards nobody mentions.
- Assess the risks. Who might be harmed and how badly, and how likely it is.
- Control the risks. What you already do, and what more you need to do.
- Record your findings. More on who has to, below.
- Review the controls. A RAMS written for a job that has since changed is not a control, it is paperwork.
Who actually has to write one down
This is where most template sites are vague, so here is the plain version.
The duty to record a risk assessment in writing falls on employers with five or more employees. Below that the assessment still has to be done, it just does not have to be written down to satisfy that particular duty.
That is the law. It is not what happens on site. Principal contractors and clients ask for a RAMS before they let anyone through the gate, whatever the size of the firm, because it is how they discharge their own duties. So a two-man firm with no recording duty still writes them, because without one there is no work.
Worth knowing as well: the CDM 2015 regulations do not use the word "RAMS" anywhere. A RAMS is an industry convention, not a statutory document. What CDM actually requires of a contractor is in regulation 13, to plan, manage, monitor and coordinate the work, and in regulation 8, that anyone appointed has the skills, knowledge and experience for it. The phrase "suitable and sufficient", which everybody quotes at you, comes from regulation 3 of the Management of Health and Safety at Work Regulations 1999 and it describes the risk assessment.
Knowing that is useful when somebody rejects your document. They are rarely quoting a regulation. They are applying their own policy, and the fix is usually specific rather than legal.
What goes in each section, and what gets it rejected
Document control. Version, date, who wrote it, who reviewed it. A RAMS with no version number cannot be shown to be the current one, which is the first thing an inspector asks.
Project information. Site address, client, principal contractor, dates. Generic entries here are the single most common reason a document is sent back: it proves the assessment was not written for this job.
Scope of works. What you are doing, in plain terms. If the scope does not match the hazards listed further down, the document contradicts itself.
Hazard identification. Each hazard, who it could harm, the risk before controls, the controls, and the risk after. Scoring every residual risk as low is a flag, not a pass.
Method statement. The sequence of work, step by step, in the order it happens. This is the part a supervisor reads on the morning of the job, so it should read like instructions, not like a policy.
PPE.Specific, with the standard where one applies. "Gloves" tells nobody anything.
Emergency arrangements. First aid, fire, evacuation, and how emergency services reach the work. On confined space and work at height this needs a rescue plan, not a phone number.
Environmental. Noise, dust, waste, spills.
Welfare. What is provided and where.
Acceptance. Names and signatures of the people who have actually read it. A briefing record with no signatures is worth nothing after an incident.
Why a downloaded template usually fails
HSE say it themselves, on their own risk assessment template page:
Do not just copy an example and put your company name to it as that would not satisfy the law and would not protect your employees. You must think about the specific hazards and controls your business needs.
That is the whole problem with a generic template in one sentence from the regulator. A bricklayer at ground level and a roofer on a pitched roof do not share hazards. A plumber on a bathroom refit and an electrician in a commercial kitchen do not share controls. A document that could belong to either belongs to neither.
HSE publish their own blank risk assessment template free, in Word and OpenDocument, and it is a perfectly good place to start if you are writing one by hand. What it cannot do is know your job.
What RAMSReady does instead
You describe the job in your own words. The generator asks you the questions a competent person would ask about that specific activity, then writes the document around your answers: the hazards that actually apply, controls written for your method, and the regulations that genuinely bear on that work rather than a list of every statute in construction.
You get a finished PDF you can issue the same morning. If the principal contractor comes back wanting something changed, you change it and reissue rather than starting again.
RAMS, risk assessment, method statement: what the words actually mean
These get used interchangeably on site and they are not the same thing, which matters when somebody tells you the wrong document is missing.
A risk assessment identifies the hazards, says who could be harmed and how, and sets out the controls. It is the thinking.
A method statement describes how the work will be done, step by step, in sequence, with the controls built into each step. It is the doing.
A RAMS is the two bound together in one document. The term is an industry convention, not a legal one, which is why you will not find it in the regulations.
A COSHH assessment is separate and specific, covering substances hazardous to health. Dust, fumes, resins, solvents, cement. A RAMS may reference it but does not replace it.
A permit to work is a control, not a document about the work. It is written authorisation for a specific high risk task, issued at the time, usually for confined space, hot work, live electrical or work affecting a structure. If a job needs a permit, the RAMS should say so and say who issues it.
Getting these straight is worth doing before an argument, because a refusal that says "your RAMS is not COSHH compliant" is usually asking for a separate assessment, not a longer RAMS.
When a principal contractor sends it back
It happens, and it is almost never about the law. The common reasons, in rough order:
- It is generic. The site address, the client or the activity does not match the job. This is the most common rejection and the quickest to fix.
- The method does not match the hazards. The method statement describes one way of working and the hazard table assesses another.
- Residual risk is low everywhere. If every hazard scores low after controls, nobody believes the assessment.
- No rescue arrangements on confined space or work at height. A phone number is not a rescue plan.
- Missing names. No author, no reviewer, no signatures from the operatives being briefed.
- Out of date. A document written for a previous phase, or past its review date.
- The wrong level of detail. Either three pages of boilerplate that says nothing about the job, or forty pages nobody will read on a Monday morning.
Ask which one it is. A specific question gets a specific answer, and most rejections are a twenty minute fix rather than a rewrite.
How often to review it
A RAMS is reviewed when the work changes, when something goes wrong or nearly does, when new plant, substances or people come onto the job, and at the review date you set on it. Reviewing means reading it against what is actually happening and changing it if it no longer matches, then reissuing and rebriefing. A review that changes nothing is still a review, as long as somebody genuinely looked.
UK Legislation Covered
Generate your RAMS now
Describe your job in plain English and get a professional RAMS, written for CDM 2015 sites, in 2 minutes.
Generate RAMS, Free PreviewYour first document is free. No card needed.