If you've been asked to provide a fencing installation RAMS before starting work, you're being asked for two linked documents: a Risk Assessment and a Method Statement. Together they demonstrate that you've thought through what could go wrong and exactly how you plan to do the job safely. This guide explains what both documents must cover for fencing work — whether you're installing close-board timber fencing, metal palisade, chain-link, or post-and-rail on a commercial or domestic site.


What Is a RAMS and Who Needs One?

A RAMS is not a single legally defined document, but it draws on real legal duties:

  • Risk Assessment — required under Regulation 3 of the Management of Health and Safety at Work Regulations 1999 for any employer or self-employed person. It must be suitable and sufficient and, where you employ five or more people, written down.
  • Method Statement — a practical, step-by-step description of how the work will be carried out safely. It is commonly required by principal contractors and clients as a condition of site access.

If the fencing work forms part of a broader construction project, the Construction (Design and Management) Regulations 2015 (CDM 2015) may also apply, placing duties on contractors to plan, manage, and monitor construction work.


Key Hazards to Identify in Your Risk Assessment

A thorough fencing installation risk assessment must address the hazards that are actually present on your specific site. Common ones include:

HazardPotential Harm
Manual handling of posts and panelsMusculoskeletal injury
Post-hole boring/excavationUnderground services strike; hand-arm vibration
Use of angle grinders / cutting toolsCuts, eye injury, sparks causing fire
Working near live traffic or publicStruck-by vehicle or pedestrian
Uneven or unstable groundSlips, trips, falls
Work at height (e.g. tall palisade, straining wires)Falls from height
Concrete mixing / post-fixing compoundsSkin/eye contact with cement or chemical fixings
Manual driving of fence postsHand-arm vibration (HAV); struck-by injury

For each hazard, assess the likelihood and severity before controls, then record the residual risk after controls are applied.


Applying the Correct Hierarchy of Controls

The hierarchy of control runs: eliminate → substitute → engineering controls → administrative controls → PPE (last resort). For fencing work, apply it practically:

Eliminate: Can post-driving be avoided by using surface-mount bolt-down bases on hard standing? This removes excavation and vibration risk entirely where ground conditions allow.

Substitute: Use a mechanical post-hole borer rather than a manual bar and spade to reduce manual handling loads — though this introduces HAV considerations you must manage.

Engineering controls: Install temporary pedestrian barriers and traffic management where work is adjacent to a road or footpath. Use ground-anchored fencing panels to segregate the work zone.

Administrative controls: Check for underground services using utility plans and a CAT scanner before any excavation (as required by safe digging practices). Brief all operatives at a site induction. Restrict working hours if noise is a concern near occupied premises.

PPE (last resort): Safety footwear (steel toecap), cut-resistant gloves, safety glasses when cutting, hi-vis vest where required by site rules, and dust mask (minimum FFP2) when cutting treated timber or concrete products.


What Your Method Statement Must Cover

The method statement explains how the work happens, step by step. For a fencing installation it should include:

  1. Scope of works — type of fencing, linear metres, post centres, fixing method
  2. Sequence of operations — site set-out, service check, excavation/boring, post installation, panel/rail fixing, finishing and waste removal
  3. Plant, tools and equipment — post-hole borer, disc cutter, compactor, concrete mixer, hand tools
  4. Materials — timber specification, concrete mix or fast-post compound, fixings
  5. Competency and supervision — who is supervising, relevant experience or training
  6. Emergency arrangements — first aid provision, nearest A&E, emergency contacts
  7. Environmental controls — disposal of concrete waste, treated timber off-cuts (which may be classified as hazardous waste)

Substances and Vibration — Two Areas Often Missed

COSHH: Pressure-treated timber (typically containing copper-based preservatives) and cement products require a COSHH assessment under the Control of Substances Hazardous to Health Regulations 2002. Identify the substance, assess the route of exposure, and specify controls — ventilation, RPE, skin protection, and waste disposal.

Hand-arm vibration: Post-driving equipment and disc cutters can expose operatives to HAV. Under the Control of Vibration at Work Regulations 2005, you must assess daily vibration exposure against the Exposure Action Value (2.5 m/s² A(8)) and Exposure Limit Value (5 m/s² A(8)). Rotate operatives and keep records.


Keeping Your RAMS Site-Specific

A generic RAMS downloaded from the internet and left unedited will not satisfy a diligent principal contractor — and more importantly, it will not protect your workers. Always:

  • Name the specific site address and client
  • Reflect the actual ground conditions and site constraints
  • Review and update the RAMS if the scope or conditions change during the job
  • Ensure all operatives have read, understood and signed the method statement before work begins

A well-written fencing installation RAMS is not just a box-ticking exercise — it is the documented thinking that keeps your team safe and demonstrates professional competence on site.