Risk Assessment · Steel Erectors

Risk Assessment for Steel Erectors

A standalone risk assessment following HSE's 5 steps: who might be harmed and how, and the controls that make the work safe. For steel erector work, it has to cover falls from height and through unprotected openings. It must include hazards specific to the actual task, site and materials.

A standalone risk assessment following HSE's 5 steps: who might be harmed and how, and the controls that make the work safe. Below: what a steel erector's Risk Assessment must contain, why they get rejected, and the hazards it has to cover, or generate one for your exact job in a couple of minutes.

A finished example

Example Risk Assessment from a similar trade (Scaffolders)

We do not have a finished Risk Assessment for steel erectors yet, so this one is from scaffolders: the layout, scoring and sign-off are what yours needs, but the hazards and method will be different for your job.

The job it was written for: “Job: erecting, altering and dismantling access scaffold. Commercial unit, occupied during working hours, 4 operatives, 1 day. Main risks: falls from height during erection; falling materials and tools; manual handling of tube and fittings.”. Names and contact details are anonymised.

EXAMPLE

Risk Assessment, Example Scaffolder Ltd

FieldDetail
Document TitleRisk Assessment: Erection, Alteration and Dismantling of Access Scaffold
CompanyExample Scaffolder Ltd
AssessorA. Supervisor
Assessment Date14 October 2026
VersionV1.0
Review Date14 October 2027

Company details

FieldDetail
Company nameExample Scaffolder Ltd
Addressto be confirmed
Registration numberto be confirmed
Phoneto be confirmed
Named supervisorA. Supervisor
Insurance valid untilto be confirmed

Task, activity and location

Activity: The erection, alteration, and dismantling of an independent access scaffold.

Location: Unit 4, Example Trading Estate, Exeter EX2 8XX.

Site context: The work takes place at an occupied commercial unit. The assessment covers a team of four operatives over one working day. This document addresses the significant findings of the risk assessment as required by The Management of Health and Safety at Work Regulations 1999. It is based on the provided job description; controls must be confirmed as implemented by the site supervisor before work starts.

Hazard assessment table

HAZARDWHO might be harmed and HOWRISK BEFORE CONTROLS: L × S = Score (Rating)CONTROL MEASURESRISK AFTER CONTROLS: L × S = Score (Rating)ACTION BY WHOMBY WHEN
Fall from heightScaffolders could fall during erection or dismantling, leading to major or fatal injuries.5 × 5 = 25 (Very High)1. Scaffold will be erected, altered and dismantled by competent CISRS carded scaffolders under the direct supervision of a CISRS Advanced Scaffolder. <br>2. Erection sequence to follow NASC guidance SG4, using the advanced guardrail system or the 'scaffolder safe zone' method to establish collective fall prevention at each lift before it is boarded out. <br>3. Personal fall protection equipment (harness and lanyard) to be used only where collective methods are not reasonably practicable, and as a secondary control. Harnesses to be inspected pre-use. <br>4. Scaffolders must not climb standards or external bracing; access to working platforms is via secured ladders. <br>5. A specific Rescue Plan is in place for any work at height (see below).3 × 5 = 15 (High)A. SupervisorBefore start
Falling materials or toolsSite operatives, client staff or members of the public could be struck by falling scaffold components or tools, causing major or fatal injuries.4 × 5 = 20 (Very High)1. The work area will be segregated from pedestrians and building occupants using barriers, cones and clear signage. A designated exclusion zone will be maintained directly below the work area. <br>2. During erection and dismantling, a 'no-go' zone will be enforced by a banksman at ground level, especially during the transfer of materials. <br>3. Tools to be carried in suitable tool belts or bags, never loose. <br>4. Materials will not be thrown from the scaffold. A gin wheel and rope will be used for lifting and lowering components, or they will be passed by hand. All lifting equipment to be subject to inspection under LOLER 1998. <br>5. Scaffold to be double-boarded on the first lift, with brick guards and toe boards fitted as work progresses.2 × 5 = 10 (High)A. SupervisorBefore start
Manual handling of scaffold componentsOperatives lifting, carrying and passing heavy or awkward scaffold tubes, boards and fittings. This can cause musculoskeletal injuries such as sprains, strains and spinal damage.4 × 3 = 12 (High)1. Operatives trained in correct kinetic lifting techniques. <br>2. Team lifting to be used for long tubes or heavy packs of fittings. <br>3. Work planned to minimise carrying distances. Materials lorry to be positioned as close to the build area as is safe. <br>4. Operatives encouraged to take regular rest breaks and to rotate tasks to avoid repetitive strain. <br>5. Gin wheel and rope to be used to lift components to height, reducing manual effort.2 × 3 = 6 (Medium)A. SupervisorBefore start
Slips, trips and falls on siteAll persons on site could trip on poorly stacked materials, offcuts or uneven ground, causing fractures, sprains or impact injuries.3 × 3 = 9 (Medium)1. A high standard of housekeeping will be maintained. Materials will be stacked neatly in designated areas, away from access routes. <br>2. Walkways and work areas to be kept clear of obstruction. Fittings to be kept in bags or containers. <br>3. All operatives to wear appropriate safety footwear with non-slip soles (BS EN ISO 20345). <br>4. Site supervisor to conduct daily checks of the work area.2 × 3 = 6 (Medium)A. SupervisorDaily
Collapse of scaffoldA full or partial collapse of the structure during or after erection could cause multiple fatal injuries to operatives and others nearby, and significant structural damage.3 × 5 = 15 (High)1. Scaffold to be erected to a recognised design standard (e.g., TG20 compliance sheet or bespoke design calculation). <br>2. Scaffold to be constructed on firm, level ground. Sole boards and base plates used on all standards. <br>3. Structure to be correctly braced, tied into the building fabric at specified intervals, and inspected by a competent person before first use and then weekly. <br>4. Scaffold not to be overloaded with materials. Loading bays will be clearly marked with maximum capacity. <br>5. Scaff-tags to be used to display inspection status.1 × 5 = 5 (Medium)A. SupervisorBefore start
Contact with live electrical servicesElectrocution from contact with overhead power lines or cables fixed to the building facade, causing severe burns or fatality. Metal scaffolding is highly conductive.4 × 5 = 20 (Very High)⛔ STOP, CONFIRM AT SITE SURVEY: <br>1. Before any work, a competent person must survey the area for overhead power lines or cables fixed to the building. <br>2. Consult HSE Guidance GS6 'Avoiding danger from overhead power lines'. Minimum safe clearance distances must be maintained. If this is not possible, the lines MUST be made dead by the network operator before work begins. <br>3. If services are identified, this must be recorded and a specific safe system of work developed and briefed to all operatives.1 × 5 = 5 (Medium)A. SupervisorBefore start
Disturbance of asbestos containing materials (ACMs)Inhalation of asbestos fibres if the scaffold is tied into building fabric (e.g., soffits, render, cement sheets) containing asbestos. This can cause fatal long-latency disease.4 × 5 = 20 (Very High)⛔ STOP, CONFIRM AT SITE SURVEY: <br>1. Before work, the client must provide a site-specific Asbestos Refurbishment/Demolition Survey or confirm from the Asbestos Register that no ACMs are present in the work area. <br>2. If a survey is unavailable for a pre-2000 building, asbestos is presumed present. No intrusive work (drilling for ties) may take place until the material is sampled and analysed by a UKAS accredited laboratory. <br>3. If ACMs are confirmed, work must stop. A licensed contractor must be engaged for any work that may disturb them. This is a requirement under the Control of Asbestos Regulations 2012.1 × 5 = 5 (Medium)A. SupervisorBefore start
Adverse weather conditionsHigh winds could make materials unstable and increase the risk of falls. Rain can make surfaces slippery. Lightning presents an electrocution risk.4 × 4 = 16 (Very High)1. Supervisor to monitor weather forecasts. Work at height to be suspended during high winds (typically >25 mph), heavy rain, or if lightning is observed. <br>2. Sheeting of the scaffold will not proceed if high winds are forecast. <br>3. Operatives to wear appropriate clothing for cold or wet conditions. <br>4. During hot weather, provide access to drinking water and encourage regular breaks in the shade.2 × 4 = 8 (Medium)A. SupervisorDaily

Hazardous substances used

This work does not involve the use of hazardous substances. No COSHH assessments are required.

Competence and training

RoleRequired competence (cards, tickets, training)Evidence held
All operativesCSCS card; site induction; manual handling trainingto be confirmed by Example Scaffolder Ltd
ScaffoldersCISRS scaffolder card for the grade of work being undertakento be confirmed by Example Scaffolder Ltd
Operatives working at heightWorking at height training; harness inspection and use trainingto be confirmed by Example Scaffolder Ltd
Named first aiderFirst Aid at Work (FAW) certificate, in dateto be confirmed by Example Scaffolder Ltd

Emergency arrangements

Named First Aider: to be confirmed. A suitably stocked first aid kit will be available on site.

Emergency Contact: A. Supervisor, 01283 000000

Nearest A&E Hospital: Royal Devon and Exeter Hospital, Exeter. Confirm before start on site.

Fire Assembly Point: To be confirmed during site induction.

In case of fire or other emergency:

  1. Stop work immediately.
  2. Raise the alarm.
  3. Proceed to the designated fire assembly point.
  4. Call 999 if required, providing the site address: Unit 4, Example Trading Estate, Exeter EX2 8XX.

Rescue plan

This plan is for the rescue of a person who has fallen from height and is suspended in a fall-arrest harness, or who is otherwise injured or incapacitated at height on the scaffold.

Named rescuer: The rescue will be led by the site supervisor (A. Supervisor), assisted by the other competent operatives on site. All operatives must be familiar with this plan.

Rescue equipment: A proprietary rescue kit will be kept immediately available at the base of the scaffold. It will include a rescue pole, cutting tool, and appropriate anchorage slings and connectors. The site supervisor is responsible for ensuring the kit is present and inspected. A mobile phone for emergency calls will be carried by the supervisor at all times.

Rescue method:

  1. The primary objective is to get the casualty to a point of safety without delay. A conscious casualty may be able to self-rescue with instruction.
  2. If self-rescue is not possible, raise the alarm to the rest of the team.
  3. One person immediately calls 999. The others prepare the rescue kit.
  4. The supervisor will assess the situation and direct the rescue. This may involve:
    • Attaching the rescue kit to a secure anchor point above the casualty.
    • Connecting the rescue device to the casualty's harness.
    • Raising the casualty slightly to release the tension on their own lanyard.
    • Disconnecting the casualty's lanyard and lowering them under control to the nearest safe platform or to the ground.
  5. If the casualty is on a platform, access will be made and first aid administered before moving them if safe to do so.

Suspension trauma: A person suspended in a harness is at immediate risk. Rescue must commence instantly. The emergency services must be informed that the casualty has been suspended in a harness so they can provide appropriate medical care.

Emergency services call sequence:

  • Who calls 999: Designated person (to be confirmed).
  • What to say: "Ambulance required for a person who has fallen from height and was suspended in a harness at Unit 4, Example Trading Estate, Exeter EX2 8XX. The casualty is [conscious/unconscious] and has been recovered to [location]."
  • Who meets ambulance: A designated person will meet the ambulance at the site entrance to direct them.
  • Who informs supervisor: The supervisor will already be aware and leading the response.

Significant findings summary

The significant risks identified are falls from height, being struck by falling materials, manual handling injuries, and potential scaffold collapse. The control measures rely on a combination of engineering and administrative controls, including the use of competent CISRS carded scaffolders, erection in accordance with NASC SG4, establishment of exclusion zones, use of mechanical lifting aids, and robust pre-use and weekly inspections. Potential high-risk hazards from asbestos and overhead services must be ruled out by a competent person during the site survey before any work begins. A detailed rescue plan is in place to manage a fall from height emergency.

Risk matrix key

LIKELIHOOD1. Very unlikely2. Unlikely3. Possible4. Likely5. Very likely
SEVERITY
5. Catastrophic510152025
4. Major48121620
3. Moderate3691215
2. Minor246810
1. Insignificant12345
Risk RatingAction Required
16-25 (Very High)Unacceptable. Stop work, implement additional controls immediately.
10-15 (High)Significant controls required. Senior management attention.
5-9 (Medium)Adequate controls required. Monitor and review.
1-4 (Low)Acceptable. Manage by routine procedures.

Review

This risk assessment will be reviewed on or before 14 October 2027, or sooner if there is any significant change to the work activity, equipment used, legislation, or following an incident.

Declaration and sign-off

I confirm that I have read and understood the contents of this risk assessment. I will comply with the specified control measures. The supervisor has confirmed that these controls are in place and are adequate to control the identified risks before work commences.

NameRoleSignatureDate
Supervisor Confirmation: A. SupervisorSupervisor

What a compliant Risk Assessment must contain

  • Hazards specific to the actual task, site and materials
  • Who might be harmed and how, for each hazard
  • The controls already in place PLUS any further action needed
  • A before/after risk score and a review date

Why a steel erector's Risk Assessment gets rejected

  • Copied from a generic example instead of written for the actual task
  • Controls that don't match what the business actually does
  • No record of who does the further actions, or by when
  • An auto-fail hazard (confined space, asbestos, live electrical) wrongly marked 'N/A'

Already have one? Check it against the standard, free.

Paste it below and it is scored the way an inspector would, with the failings that would get it rejected. No sign-up.

Steel Erectors hazards it must cover

Typical steel erector work, meaning structural steel erection, bolting, decking and edge protection on frames, brings hazards a Risk Assessment has to address:

  • falls from height and through unprotected openings
  • crane and lifting operations (LOLER 1998)
  • instability of partially erected frames
  • dropped tools and bolts
  • hot works during site welding and cutting

Generate your Risk Assessment in minutes

Built to the correct published standard for a steel erector: specific controls, the right legal basis, a review date and a sign-off section you can operate.

Start your Risk Assessment

FAQ

Do steel erectors legally need a Risk Assessment?

A standalone risk assessment following HSE's 5 steps: who might be harmed and how, and the controls that make the work safe. For steel erector work, meaning structural steel erection, bolting, decking and edge protection on frames, it is the document a client, principal contractor or inspector expects to see, grounded in MHSWR 1999 reg 3 (HSE): the 5-step method (INDG163).

What must a steel erector's Risk Assessment contain?

At minimum: hazards specific to the actual task, site and materials; who might be harmed and how, for each hazard; the controls already in place PLUS any further action needed; A before/after risk score and a review date.

Why does a steel erector's Risk Assessment get rejected?

The usual reasons: copied from a generic example instead of written for the actual task; controls that don't match what the business actually does; no record of who does the further actions, or by when; an auto-fail hazard (confined space, asbestos, live electrical) wrongly marked 'N/A'.

Which regulation is a steel erector's Risk Assessment written under?

MHSWR 1999. The full text is on legislation.gov.uk at https://www.legislation.gov.uk/uksi/1999/3242/contents.

How fast can I get a Risk Assessment?

A couple of minutes. Describe the job, and RAMSReady writes a Risk Assessment for your exact steel erector job live against the correct standard, with a review date and a sign-off/records section.

Not writing this one today?

We will email you a one page overview of what RAMSReady covers, so you have it when you need it.

Want to see how it would work for your firm?

Tell us roughly what you run and who keeps your records, and we will come back to you.

Related guides

Other documents for Steel Erectors

Similar trades

Templates and tools