Method Statement · Tarmac & Surfacing Contractors

Method Statement for Tarmac & Surfacing Contractors

A safe system of work: the numbered, step-by-step sequence for carrying out the task safely, that an operative can actually follow. For surfacing contractor work, it has to cover burns from hot asphalt (up to 180°C). It must include A numbered sequence from set-up to clean-down.

A safe system of work: the numbered, step-by-step sequence for carrying out the task safely, that an operative can actually follow. Below: what a surfacing contractor's Method Statement must contain, why they get rejected, and the hazards it has to cover, or generate one for your exact job in a couple of minutes.

A finished example

Example Method Statement from a similar trade (Groundworkers)

We do not have a finished Method Statement for tarmac & surfacing contractors yet, so this one is from groundworkers: the layout, scoring and sign-off are what yours needs, but the hazards and method will be different for your job.

The job it was written for: “Job: excavation, drainage, foundations and external works. Commercial unit, occupied during working hours, 2 operatives, 1 day. Main risks: excavation collapse and buried services; plant and pedestrian interface; manual handling.”. Names and contact details are anonymised.

EXAMPLE

Method Statement: Example Groundworker Ltd

Document Control

FieldDetail
Document TitleMethod Statement: Excavation & Associated Works
Project / SiteUnit 4, Example Trading Estate, Exeter EX2 8XX
CompanyExample Groundworker Ltd
AuthorA. Supervisor
Date14 October 2026
VersionV1.0
Review Date14 October 2027

Company Details

FieldDetail
Company NameExample Groundworker Ltd
Addressto be confirmed
Registration Numberto be confirmed
Phoneto be confirmed
Named SupervisorA. Supervisor
Insurance Valid Untilto be confirmed

Scope & Description of Works

This method statement details the safe system of work for excavation, drainage, foundation preparation and external works at the specified commercial site. The site will remain occupied during working hours, requiring careful management of the interface between works and site occupants.

The work will be undertaken by a team of two operatives over one day.

This work is classified as construction work under the Construction (Design and Management) Regulations 2015. All work will be carried out in accordance with the site rules and the construction phase plan provided by the Principal Contractor, Example Client.

Site, Access & Logistics

Site Address: Unit 4, Example Trading Estate, Exeter EX2 8XX.

Access & Egress: Vehicle and pedestrian access will be via the main estate road entrance. The supervisor will confirm the designated access route, parking and set-down area with the site manager before work commences.

Work Area & Exclusion Zones:

  • The work area will be clearly delineated using Chapter 8 barriers (or equivalent solid fencing) to create a secure exclusion zone.
  • Warning signs, including 'Deep Excavations', 'Construction Site. Keep Out' and 'Caution: Heavy Plant Operating', will be fixed to the perimeter.
  • Access to the work area will be restricted to authorised personnel only.
  • A banksman will control all vehicle movements into and out of the work area.

Deliveries: Deliveries of plant, materials and trench support systems will be scheduled with the site manager to minimise disruption. All delivery vehicles will be met and directed by a trained banksman.

Key Principles / Safe-Work Basis

All excavation work will be conducted on the basis that no ground can be relied upon to stand unsupported. Suitable and sufficient excavation support (trench sheets, props) or ground battering to a safe angle will be planned and available on site before any digging begins.

All ground will be presumed to contain live buried services until proven otherwise by a thorough service location procedure using service plans and cable avoidance tools.

Sequence of Operations

The work will be completed in the following numbered sequence.

1. Site Set-up and Preparation

  1. All operatives will attend the site induction provided by Example Client.
  2. The supervisor will brief all operatives on this method statement and the associated risk assessment.
  3. The work area will be inspected for hazards. All controls identified in the risk assessment must be in place before work starts.
  4. Establish the exclusion zone using Chapter 8 barriers and appropriate signage.
  5. Position a fire extinguisher (powder) and a fully stocked first aid kit in a designated, accessible location.

2. Location of Buried Services

  1. Obtain and review all available service plans (e.g. STATS, utility provider drawings) for the work area.
  2. Using a CAT and Genny (Cable Avoidance Tool and Signal Generator), a competent operative will scan the entire proposed excavation area.
  3. The area will be scanned first in Power mode, then Radio mode, then in Genny mode with the signal generator connected to known services or induced into the ground.
  4. Mark the identified location of all detected services on the ground using spray paint, following the standard colour-coding system.
  5. Dig trial holes by hand using insulated tools (HSG47 safe digging practice) to physically confirm the location, depth and type of services. No mechanical excavation is permitted within 0.5 metres of a marked service.

3. Mechanical Excavation

  1. A pre-use check will be completed on the excavator by a competent operator, and the findings recorded.
  2. The operator will ensure the excavator's warning beacons and alarms are functioning correctly.
  3. A banksman will be used to direct all machine movements, ensuring a safe distance is maintained from pedestrians, structures and live services. The banksman and operator will agree on a clear system of hand signals before starting.
  4. Excavation will proceed in shallow lifts, with the operator remaining vigilant for any visual signs of buried services (e.g. marker tape, ducting).
  5. Spoil will be placed at a safe distance from the excavation edge (minimum 1.0 metre) to prevent it from falling in and to avoid overloading the sides.

4. Ground Support & Access

  1. As the excavation reaches a depth of 1.2 metres, or sooner if ground conditions are poor, work will pause to install trench support.
  2. Trench sheets and props will be installed progressively from the top down as the excavation deepens, in accordance with the manufacturer's instructions.
  3. No person will enter an unsupported excavation deeper than 1.2 metres.
  4. A securely footed ladder will be placed to provide safe access and egress. The ladder must extend at least 1 metre above the excavation edge.

5. Drainage, Foundations & External Works

  1. Materials (pipes, stone, concrete) will be lowered into the excavation using mechanical means or safe manual handling techniques. Materials will not be thrown into the excavation.
  2. Operatives will wear appropriate PPE for the task (e.g. waterproof gloves for drainage, knee pads for kerbing).
  3. Concrete will be placed carefully to avoid splash hazards. Wash-down of concrete equipment will occur in a designated area away from drains.

6. Backfilling and Reinstatement

  1. Trench supports will be removed in the reverse order of installation (from the bottom up) as backfilling progresses. Operatives will not enter the excavation during support removal.
  2. Backfill material will be compacted in layers as specified.
  3. The surface will be reinstated as per the client's specification.

7. Demobilisation and Housekeeping

  1. All tools, plant and equipment will be cleaned and removed from the work area.
  2. All waste and surplus materials will be removed from site and disposed of at a licensed facility.
  3. The exclusion zone barriers and signs will be removed.
  4. The supervisor will inspect the area with the site manager to confirm the work is complete and the area is left in a safe, clean and tidy condition.

Plant, Equipment & Materials

ItemSafe Use Requirements
Mini Excavator (e.g. 1.5 tonne)To be operated only by a trained and certified (CPCS/NPORS) operator. Daily pre-use checks required. Lifting operations must comply with LOLER 1998.
Dumper (if required)To be operated only by a trained and certified operator. Must not be overloaded. Banksman to be used for reversing.
Cable Avoidance Tool & Signal GeneratorTo be used only by a competent person with recent training. Must be function-tested before each use.
Trench Sheets & PropsMust be visually inspected before use for damage. To be installed as per manufacturer's instructions by competent persons.
Hand Tools (shovels, picks, etc.)Visually inspect before use. Use insulated tools (e.g. fibreglass shafts) for safe digging.
Cement & ConcreteSee COSHH Assessment. Wear appropriate PPE (gloves, goggles).
Aggregates & PipesStore securely to prevent collapse or rolling. Use correct manual handling techniques.

Hazardous Substances Used

SubstanceWhere usedHazardControlsCOSHH assessment ref.
Cement / ConcreteFoundations and drainage works.Alkaline. Can cause serious skin burns and eye damage. Inhalation of dust is harmful.Wear waterproof gloves (BS EN 374), eye protection (BS EN 166) and FFP3 dust mask (BS EN 149). Provide eye wash station.COSHH-1 (generate)
Silica Dust (Respirable Crystalline Silica)Created when cutting or drilling concrete, stone or kerbs.Inhalation can cause silicosis, a serious and irreversible lung disease.Use water suppression or on-tool dust extraction. Wear FFP3 respiratory protection. Minimise cutting on site where possible.COSHH-2 (generate)
Diesel FuelRefuelling plant.Flammable. Skin irritant. Harmful if ingested or inhaled. Environmental hazard.No smoking/naked flames. Use a proper filling nozzle. Wear nitrile gloves. Have a spill kit available.COSHH-3 (generate)

Competence and Training

RoleRequired competence (cards, tickets, training)Evidence held
All operativesCSCS card; site induction; manual handling trainingto be confirmed by Example Groundworker Ltd
Excavation teamCAT and Genny (cable avoidance tool and signal generator) training; Safe Digging Practice (HSG47) awareness.to be confirmed by Example Groundworker Ltd
Plant operatorsCPCS or NPORS card for the specific category of excavator or dumper used.to be confirmed by Example Groundworker Ltd
Named first aider (to be confirmed)First Aid at Work (FAW) certificate, in date.to be confirmed by Example Groundworker Ltd
SupervisorSSSTS or SMSTS certificate; competent in risk assessment and method statement implementation.to be confirmed by Example Groundworker Ltd

The work will be directly supervised by the named competent supervisor: A. Supervisor.

Key Controls

The following key hazards and controls from the risk assessment must be implemented.

HazardControl MeasuresCompleted, date & initials
Excavation CollapseNo entry into excavations over 1.2m deep unless supported by trench sheets/props or battered to a safe angle. Spoil and plant kept away from excavation edges. Daily inspections of excavations by a competent person.
Contact with Live Buried ServicesAdherence to HSG47. Use of service plans and CAT & Genny before any digging. Use of insulated hand tools for trial holes. Mechanical excavation prohibited within 0.5m of known services.
Struck by Moving PlantA competent banksman will control all vehicle and plant movements. Segregation of pedestrians and plant with physical barriers. Use of vehicle warning beacons and reversing alarms. High-visibility clothing to be worn at all times.
Manual Handling InjuriesMechanical aids (e.g. excavator) to be used for lifting heavy materials where possible. Where manual handling is unavoidable, use correct kinetic lifting techniques. Two-person lifts for awkward or heavy items.
Slips, Trips & FallsMaintain good housekeeping. Keep work area tidy and free from obstructions. Cordon off uneven ground. Wear safety boots with good grip.
⛔ STOP, CONFIRM AT SITE SURVEY: AsbestosThe age of the building and ground is unknown. Work must not proceed if there is any suspicion of Asbestos Containing Materials (ACMs) in the ground (e.g. old pipework, buried debris) or building fabric. Stop work, report to the site manager and await the results of an asbestos survey by a qualified person before proceeding. Adhere to the Control of Asbestos Regulations 2012.
⛔ STOP, CONFIRM AT SITE SURVEY: Confined SpacesIf the drainage work involves entry into any manhole, deep inspection chamber, or other substantially enclosed space, this is a confined space. Work must not proceed. A specific safe system of work, including emergency rescue arrangements, must be produced in line with the Confined Spaces Regulations 1997 before any entry is considered.

PPE

All PPE must be compliant with the Personal Protective Equipment at Work Regulations 2022 and conform to the relevant BS EN standards.

ItemStandard
Safety Helmet (Hard Hat)BS EN 397
High-Visibility Clothing (Jacket/Vest)BS EN ISO 20471 Class 2 or 3
Steel Toe-Capped Safety Boots (with mid-sole protection)BS EN ISO 20345
Safety Glasses / GogglesBS EN 166
Heavy-Duty Work Gloves (Cut-resistant)BS EN 388
Hearing Protection (if required by noise assessment)BS EN 352
Respiratory Protection (FFP3 Dust Mask for silica/cement dust)BS EN 149

Emergency & First Aid Arrangements

Site First Aider: to be confirmed. Location of First Aid Kit: Within the site welfare facilities / company vehicle. Emergency Contact: A. Supervisor, 01283 000000. Accident Reporting: All accidents, incidents and near misses, no matter how minor, must be reported to the supervisor immediately. Serious incidents will be reported under RIDDOR 2013. Nearest A&E Hospital: Royal Devon and Exeter Hospital, Exeter. Confirm before start on site. Fire Assembly Point: As designated by the site manager during induction.

Rescue Plan

This rescue plan is specifically for an emergency within the excavation.

Rescuer Role: The second operative on site will act as the 'Top Person' and initiate the rescue. The supervisor will take command on arrival. No one should enter the excavation to attempt a rescue if there is a risk of collapse or hazardous atmosphere.

Rescue Equipment:

  • A securely positioned ladder, always available in the excavation.
  • Mobile phone for emergency services.
  • First aid kit.

Rescue Method (Collapse / Injury in excavation):

  1. Do NOT enter the excavation.
  2. Raise the alarm immediately, shouting to attract attention and calling the site supervisor.
  3. The Top Person is to call the emergency services immediately. Dial 999.
  4. Provide the operator with the exact site address: Unit 4, Example Trading Estate, Exeter EX2 8XX. State the nature of the emergency (e.g. 'man injured in a collapsed trench').
  5. If safe to do so, attempt to communicate with the casualty. Reassure them that help is on its way.
  6. If the casualty is accessible from the top edge without entering, and is not trapped, offer the ladder or a hand to assist them out. Do not pull them if they are injured.
  7. Send one person to the site entrance to meet and direct the emergency services.
  8. Preserve the scene for investigation.

Sign-off

I have read and understood this Method Statement. I agree to work in accordance with its requirements at all times. I will report any safety concerns to my supervisor immediately.

NameRoleSignatureDate

Supervisor's Declaration: I confirm that the required actions have been completed and the control measures are in place and are being monitored.

NameRoleSignatureDate
A. SupervisorSupervisor

What a compliant Method Statement must contain

  • A numbered sequence from set-up to clean-down
  • The specific plant, equipment and isolation points named at each step
  • Measurable checks where a step proves safety (e.g. prove dead, hold zero-pressure 30s)
  • Competence requirements and PPE

Why a surfacing contractor's Method Statement gets rejected

  • Abstract steps ('isolate and verify') with nothing measurable
  • A likelihood × severity scoring table bolted on (that belongs in the risk assessment)
  • Steps that skip the actual sequence a job really follows
  • No named competent person for the steps that need one

Already have one? Check it against the standard, free.

Paste it below and it is scored the way an inspector would, with the failings that would get it rejected. No sign-up.

Tarmac & Surfacing Contractors hazards it must cover

Typical surfacing contractor work, meaning roads, car parks, driveways and footpaths in hot-laid asphalt, brings hazards a Method Statement has to address:

  • burns from hot asphalt (up to 180°C)
  • bitumen fumes and RCS dust from planing
  • being struck by pavers, rollers and delivery lorries
  • working beside live traffic
  • noise and hand-arm vibration from compactors

Generate your Method Statement in minutes

Built to the correct published standard for a surfacing contractor: specific controls, the right legal basis, a review date and a sign-off section you can operate.

Start your Method Statement

FAQ

Do tarmac & surfacing contractors legally need a Method Statement?

A safe system of work: the numbered, step-by-step sequence for carrying out the task safely, that an operative can actually follow. For surfacing contractor work, meaning roads, car parks, driveways and footpaths in hot-laid asphalt, it is the document a client, principal contractor or inspector expects to see, grounded in the recognised safe-system-of-work format (HSE guidance).

What must a surfacing contractor's Method Statement contain?

At minimum: A numbered sequence from set-up to clean-down; the specific plant, equipment and isolation points named at each step; measurable checks where a step proves safety (e.g. prove dead, hold zero-pressure 30s); competence requirements and PPE.

Why does a surfacing contractor's Method Statement get rejected?

The usual reasons: abstract steps ('isolate and verify') with nothing measurable; A likelihood × severity scoring table bolted on (that belongs in the risk assessment); steps that skip the actual sequence a job really follows; no named competent person for the steps that need one.

Which regulation is a surfacing contractor's Method Statement written under?

MHSWR 1999. The full text is on legislation.gov.uk at https://www.legislation.gov.uk/uksi/1999/3242/contents.

How fast can I get a Method Statement?

A couple of minutes. Describe the job, and RAMSReady writes a Method Statement for your exact surfacing contractor job live against the correct standard, with a review date and a sign-off/records section.

Not writing this one today?

We will email you a one page overview of what RAMSReady covers, so you have it when you need it.

Want to see how it would work for your firm?