Method Statement Template for UK Construction

A method statement describes the step-by-step safe working procedure for a construction activity. Generate one in 2 minutes, tailored to your specific job.

What is a Method Statement?

A method statement (also called a safe system of work or SSOW) is a document that describes in a logical sequence exactly how a job is to be carried out safely. It includes the hazards involved and the precautions needed to mitigate the risks.

Method statements are a key part of your health and safety management system under the Management of Health and Safety at Work Regulations 1999. They demonstrate to principal contractors, clients, and HSE that you have planned your work safely.

What Should a Method Statement Include?

  • Project details: site, client, contractor, dates
  • Description of the work to be carried out
  • Sequence of operations: step-by-step procedure
  • Plant and equipment to be used
  • Materials required
  • Labour resources and competency requirements
  • Hazards identified at each stage
  • Control measures for each hazard
  • PPE requirements
  • Supervision arrangements
  • Emergency procedures
  • Waste management and environmental controls
  • Permits to work required (hot works, confined space, etc.)
  • Sign-off by all operatives before work begins

When Do You Need a Method Statement?

You need a method statement for any construction activity where there is a significant risk of harm. In practice, most principal contractors require one for every trade working on their site.

High-risk activities (working at height, hot works, confined space entry, demolition, excavation, work near live services) always require a detailed method statement with specific control measures.

Generate your method statement

Describe your job and get a professional method statement with step-by-step procedures, hazard controls, and PPE requirements.

Generate Method Statement

Your first document is free. No card needed.

Method Statement: common questions

What must a Method Statement contain?

At minimum: A numbered sequence from set-up to clean-down; the specific plant, equipment and isolation points named at each step; measurable checks where a step proves safety (e.g. prove dead, hold zero-pressure 30s); competence requirements and PPE.

Why does a Method Statement get rejected?

The usual reasons: abstract steps ('isolate and verify') with nothing measurable; A likelihood × severity scoring table bolted on (that belongs in the risk assessment); steps that skip the actual sequence a job really follows; no named competent person for the steps that need one.

Which regulation is a Method Statement written under?

MHSWR 1999. The full text is on legislation.gov.uk at https://www.legislation.gov.uk/uksi/1999/3242/contents.