Method Statement · Fire Alarm & Security Installers

Method Statement for Fire Alarm & Security Installers

A safe system of work: the numbered, step-by-step sequence for carrying out the task safely, that an operative can actually follow. For fire and security installer work, it has to cover working at height on steps and towers in occupied premises. It must include A numbered sequence from set-up to clean-down.

A safe system of work: the numbered, step-by-step sequence for carrying out the task safely, that an operative can actually follow. Below: what a fire and security installer's Method Statement must contain, why they get rejected, and the hazards it has to cover, or generate one for your exact job in a couple of minutes.

A finished example

Example Method Statement from a similar trade (Ductwork Installers)

We do not have a finished Method Statement for fire alarm & security installers yet, so this one is from ductwork installers: the layout, scoring and sign-off are what yours needs, but the hazards and method will be different for your job.

The job it was written for: “Job: ventilation ductwork, kitchen extract, AHUs and fire dampers in commercial buildings. Commercial unit, occupied during working hours, 4 operatives, 2 days. Main risks: working at height on towers and MEWPs with heavy sections; cuts from sheet-metal edges; manual handling of long duct runs.”. Names and contact details are anonymised.

EXAMPLE

Method Statement: Ductwork Installation

FieldDetail
Document TitleMethod Statement: Ductwork Installation
CompanyExample Ductwork Installer Ltd
Site AddressUnit 4, Example Trading Estate, Exeter EX2 8XX
AuthorA. Supervisor
Issue Date14 October 2026
VersionV1.0
Review Date14 October 2027

Company details

FieldDetail
Company nameExample Ductwork Installer Ltd
Addressto be confirmed
Registration numberto be confirmed
Phoneto be confirmed
Named supervisorA. Supervisor
Insurance valid untilto be confirmed

Scope & Description of works

This method statement details the safe system of work for the installation of ventilation ductwork, kitchen extract systems, Air Handling Units (AHUs), and associated fire dampers within an occupied commercial unit.

The works will be undertaken by a team of four operatives over an estimated two-day period. Key tasks include the delivery and distribution of materials, mechanical lifting and manual handling of ductwork sections, working at height using mobile access towers and MEWPs, cutting and fixing ductwork, installing AHUs, and conducting hot works for connections or modifications.


Site, access & logistics

Site Access and Egress

  1. All operatives will report to the site reception on first arrival to sign in and undergo the client's site induction.
  2. Vehicles will park only in designated areas. Access routes for other site users and emergency services will be kept clear at all times.
  3. Materials will be delivered to a pre-agreed storage area, located away from main thoroughfares and emergency exits.

Work Area Management

  1. The immediate work area will be segregated from building occupants using physical barriers (e.g. Chapter 8 barriers) and clear signage.
  2. Where overhead work is performed, the area below will be established as a strict exclusion zone. No unauthorised personnel may enter.
  3. Tools and materials will be kept within the designated work area to minimise slip and trip hazards. The area will be kept tidy throughout the shift.

Key principles / Safe-work basis

Permit-to-Work Systems

  1. A Permit to Work for Hot Works will be obtained from the client or site manager before any cutting, grinding or welding begins. All conditions of the permit will be followed without deviation.
  2. An Electrical Permit to Work or equivalent isolation certificate will be obtained before connecting or modifying any electrical systems, including AHUs.

Competence

All works will be carried out by demonstrably competent and trained operatives, under the direct supervision of the named site supervisor. Specific competence requirements are detailed in the 'Competence and training' section of this document.


Sequence of operations

1. Site set-up and preparation

  1. The supervisor will conduct a toolbox talk with all operatives to communicate the content of this method statement and the associated risk assessment.
  2. Confirm all required permits (Hot Works, Electrical Isolation) are in place and signed by the relevant authorities.
  3. Establish segregated work zones and exclusion areas using barriers and signs, particularly where work at height or hot works will occur.
  4. Inspect all work equipment before use, including MEWPs, mobile access towers, lifting equipment, and power tools, in line with PUWER 1998 and LOLER 1998. Defective equipment will be removed from service immediately.
  5. Check the location of site fire-fighting equipment, first aid kits, and emergency muster points.
  6. The work area will be inspected for housekeeping standards before work begins.

2. Manual handling and material distribution

  1. Ductwork sections and AHUs will be moved from the storage area to the point of installation using mechanical aids (e.g. trolleys, pallet trucks) wherever practicable.
  2. For manual handling of long or heavy duct sections, a minimum of two operatives will be used. The principles of kinetic lifting will be applied. A clear path will be established before any load is moved.
  3. Ductwork sections will be stored securely on-site, stacked flat and not creating a toppling or trip hazard.

3. Work at height: Access and installation

  1. Select and use appropriate access equipment following the work at height hierarchy. Mobile access towers (PASMA trained operatives) or MEWPs (IPAF trained operatives) will be the primary means of access. Ladders will be used only for short-duration tasks where a risk assessment confirms it is safe to do so.
  2. Pre-use checks will be completed on all access equipment. MEWPs will be positioned on firm, level ground. Outriggers will be fully deployed on stabiliser pads.
  3. When using MEWPs, operatives will wear a full-body harness with a short restraint lanyard attached to a designated anchor point in the basket.
  4. Tools and materials will be transported to height securely, either within the MEWP basket (not exceeding the Safe Working Load) or using a certified gin wheel and rope. Materials will never be thrown to or from the working platform.
  5. Ductwork sections will be lifted into position using appropriate lifting accessories (e.g. certified slings, shackles). Operatives will keep all body parts clear during the lifting phase.
  6. Ductwork will be securely fixed using specified brackets and fasteners before moving to the next section.

4. Cutting and fixing operations

  1. Operatives will wear cut-resistant gloves (BS EN 388) and safety glasses (BS EN 166) when handling and cutting sheet metal.
  2. Power tools (e.g. drills, grinders) will be 110V CTE supply or battery-powered. Pre-use visual checks for damage to casings, cables, and plugs will be conducted.
  3. Where cutting or grinding is required (hot works), a permit will be active. A fire watch will be posted, a suitable fire extinguisher will be immediately to hand, and nearby combustible materials will be removed or protected with fire-retardant blankets.

5. AHU installation and connection

  1. The AHU will be lifted into its final position using a suitable mechanical lift (e.g. genie lift, scissor lift). The lift will be positioned on a firm, level surface and operated by a competent person.
  2. The unit will be securely fixed in position as per manufacturer's instructions.
  3. Electrical connections to the AHU will only be performed by a competent electrician after formal electrical isolation has been proven. The circuit will be locked off, tagged, and proven dead at the point of work using a calibrated voltage indicator.

6. Completion and clean-down

  1. On completion of the installation, all tools, surplus materials, and waste will be removed from the work area.
  2. The area will be swept clean, leaving it in a safe condition. Waste materials will be segregated and disposed of in the client's designated skips.
  3. All permits to work will be signed off and returned to the site manager.
  4. The supervisor will inspect the completed works with the client representative before demobilising from the site.

Plant, equipment & materials

ItemSafe Use Requirements
Mobile Elevating Work Platform (MEWP)Operated only by trained (IPAF) personnel. Pre-use checks, harness and lanyard use mandatory. Positioned on firm, level ground. SWL not to be exceeded.
Mobile access towerErected, inspected, and dismantled only by trained (PASMA) personnel. Stable, level base. Green tag displayed when safe for use.
Ladders / StepladdersFor short-duration, light-duty tasks only. Positioned on a firm, level base at the correct angle. Maintained three points of contact.
Electric drills, grinders, saws110V or cordless. Visually inspect cables, plugs, and guards before use. Use appropriate PPE (glasses, gloves).
Hand tools (snips, screwdrivers etc.)Inspect for damage before use. Use the correct tool for the task. Wear cut-resistant gloves when handling sheet metal.
Lifting equipment (slings, shackles)LOLER certified and within inspection date. Visually checked for defects before each use. Used within SWL.
Galvanised steel ductworkHandle with cut-resistant gloves. Store securely.
Fire dampers / AHUsHandle in accordance with manufacturer's instructions. Use mechanical aids for lifting where possible.

Hazardous substances used

SubstanceWhere usedHazardControlsCOSHH assessment ref.
Metal dust/fumeCutting, grinding and welding ductworkInhalation may cause respiratory irritation. Fume can be toxic.Use in well-ventilated area. RPE (FFP3) for grinding. Local exhaust ventilation (LEV) for welding.COSHH-1 (generate)
Sealants / AdhesivesSealing duct jointsSkin and eye irritation. Vapour inhalation.Wear nitrile gloves and safety glasses. Ensure good ventilation. Refer to Safety Data Sheet (SDS).COSHH-2 (generate)
Cleaning solventsDegreasing surfacesFlammable. Skin irritation. Vapour inhalation.No ignition sources nearby. Wear nitrile gloves and safety glasses. Ensure good ventilation. Refer to SDS.COSHH-3 (generate)

Competence and training

RoleRequired competence (cards, tickets, training)Evidence held
All operativesCSCS card; site induction; manual handling trainingto be confirmed by Example Ductwork Installer Ltd
Operatives working at heightWorking at height training; PASMA for mobile access towers; IPAF (3a or 3b) for MEWPs; harness inspection and use training where harnesses are wornto be confirmed by Example Ductwork Installer Ltd
Hot works operativesHot work permit training; competence in the cutting or grinding process usedto be confirmed by Example Ductwork Installer Ltd
Fire watchFire watch and fire extinguisher trainingto be confirmed by Example Ductwork Installer Ltd
Named first aider (to be confirmed)First Aid at Work (FAW) certificate, in dateto be confirmed by Example Ductwork Installer Ltd

Key controls

This table summarises key controls identified in the risk assessment. The named supervisor is responsible for confirming their implementation on site.

HazardControl Measures (Recommended)Completed, date & initials
Slips, trips, falls on same levelMaintain good housekeeping. Cordon off work areas. Ensure materials are stored safely.
Work at height (falls from MEWPs, towers)Use MEWPs/towers as primary access. Ensure operators are IPAF/PASMA trained. Conduct pre-use checks. Use harness/lanyard in MEWP. Establish exclusion zones below.
Falling materialsSecure tools and materials at height. Use toe boards on towers. Enforce exclusion zones below. Do not overload platforms.
Manual handling injuriesUse mechanical aids where practicable. Use team lifts for long/heavy items. Provide manual handling training.
Cuts from sharp metal edgesMandate use of cut-resistant gloves (BS EN 388) when handling all sheet metal components.
Fire (Hot Works)Operate under a Hot Work Permit. Remove or protect combustibles. Have a fire extinguisher and trained fire watch present. Maintain watch for 60 mins post-work.
Electric shockAll portable tools to be 110V or cordless. Formal isolation, lock-out, tag-out, and proving dead before working on any existing electrical system (e.g. AHU supply).
Contact with live servicesReview service drawings before any drilling or fixing into building fabric. Use a cable avoidance tool (CAT scanner) where locations are uncertain.
⛔ STOP, CONFIRM AT SITE SURVEY: AsbestosThe building age is unknown. Work is prohibited until the client provides an up-to-date Asbestos Register, in compliance with the Control of Asbestos Regulations 2012. If asbestos is identified in the work area, a licensed contractor must manage it before this work can proceed.
⛔ STOP, CONFIRM AT SITE SURVEY: Confined spacesConfirm if work requires entry or partial entry into existing duct systems, plant rooms, or restricted roof voids. If so, work is prohibited until a full confined space risk assessment and safe system of work, including emergency rescue arrangements, are developed in line with the Confined Spaces Regulations 1997.

PPE

ItemStandard
Safety helmetBS EN 397
Safety footwear (with midsole protection)BS EN ISO 20345
High-visibility clothingBS EN ISO 20471
Safety glasses / GogglesBS EN 166
Cut-resistant glovesBS EN 388
Hearing protection (for power tool use)BS EN 352
Respiratory Protection (dust/fumes)BS EN 149 (FFP3)
Full body harness and restraint lanyardBS EN 361 / BS EN 354

Emergency & First Aid arrangements

RoleDetail
Site supervisor / emergency contactA. Supervisor, 01283 000000
Named first aiderto be confirmed
First aid kit locationIn company vehicle and site office.
Nearest 24-hour A&E HospitalRoyal Devon and Exeter Hospital, Exeter. Confirm before start on site.
Emergency procedureIn the event of an emergency, raise the alarm. Call 999. State the nature of the emergency and provide the site address: Unit 4, Example Trading Estate, Exeter EX2 8XX. Send someone to meet the emergency services at the site entrance.
Fire assembly pointAs designated by the client's site induction.

Rescue plan

Work at height rescue

  • Responsible person for rescue: A. Supervisor (or another competent person on site).
  • Rescue equipment: The MEWP has ground-level emergency controls. A fully charged mobile phone for emergency calls. Access ladders will be available on site.
  • Rescue method (MEWP):
    1. In the event of a platform malfunction or medical emergency, the second operative on the ground will initiate the rescue.
    2. The area below the MEWP will be cleared.
    3. The ground-based operative will use the emergency lowering controls on the MEWP chassis to bring the basket safely to the ground.
    4. If an operative has fallen and is suspended by their lanyard, the basket will be lowered immediately to minimise suspension time.
  • Rescue method (Mobile Tower):
    1. In the event of an incident, another operative will ascend the tower (if safe to do so) to provide immediate assistance.
    2. If the casualty can descend with assistance, they will be helped down via the internal ladder.
    3. If the casualty is incapacitated, the emergency services will be called to perform the rescue. Operatives will not attempt to move an unconscious or seriously injured person.
  • Suspension trauma: Rescue of a suspended person must be initiated immediately. Any delay can be fatal. When calling 999, inform the operator that a person has been suspended in a fall-arrest harness.
  • Emergency call sequence:
    1. One person dials 999/112. State: "Ambulance/Fire, person fallen from height".
    2. Give address: Unit 4, Example Trading Estate, Exeter EX2 8XX.
    3. Give details: Nature of injuries, if known. State that the person was suspended in a harness.
    4. A designated person will meet the ambulance at the trading estate entrance to direct them.
    5. The supervisor must be informed immediately.

Sign-off

I have read and understood this Method Statement and will comply with its requirements. I confirm I have received a briefing on its contents and have had the opportunity to ask questions.

NameRoleSignatureDate
Supervisor
Operative
Operative
Operative
Operative

Supervisor's Confirmation

I confirm that the control measures detailed in this document have been implemented, and that all operatives have been briefed and have signed above to acknowledge their understanding.

NameRoleSignatureDate
A. SupervisorSupervisor

What a compliant Method Statement must contain

  • A numbered sequence from set-up to clean-down
  • The specific plant, equipment and isolation points named at each step
  • Measurable checks where a step proves safety (e.g. prove dead, hold zero-pressure 30s)
  • Competence requirements and PPE

Why a fire and security installer's Method Statement gets rejected

  • Abstract steps ('isolate and verify') with nothing measurable
  • A likelihood × severity scoring table bolted on (that belongs in the risk assessment)
  • Steps that skip the actual sequence a job really follows
  • No named competent person for the steps that need one

Already have one? Check it against the standard, free.

Paste it below and it is scored the way an inspector would, with the failings that would get it rejected. No sign-up.

Fire Alarm & Security Installers hazards it must cover

Typical fire and security installer work, meaning fire-alarm, intruder, CCTV and access-control installation in occupied buildings, brings hazards a Method Statement has to address:

  • working at height on steps and towers in occupied premises
  • drilling into ceilings and walls with hidden services and asbestos
  • electric shock on panel and mains work
  • lone working out of hours
  • disruption to existing fire cover while systems are down

Generate your Method Statement in minutes

Built to the correct published standard for a fire and security installer: specific controls, the right legal basis, a review date and a sign-off section you can operate.

Start your Method Statement

FAQ

Do fire alarm & security installers legally need a Method Statement?

A safe system of work: the numbered, step-by-step sequence for carrying out the task safely, that an operative can actually follow. For fire and security installer work, meaning fire-alarm, intruder, CCTV and access-control installation in occupied buildings, it is the document a client, principal contractor or inspector expects to see, grounded in the recognised safe-system-of-work format (HSE guidance).

What must a fire and security installer's Method Statement contain?

At minimum: A numbered sequence from set-up to clean-down; the specific plant, equipment and isolation points named at each step; measurable checks where a step proves safety (e.g. prove dead, hold zero-pressure 30s); competence requirements and PPE.

Why does a fire and security installer's Method Statement get rejected?

The usual reasons: abstract steps ('isolate and verify') with nothing measurable; A likelihood × severity scoring table bolted on (that belongs in the risk assessment); steps that skip the actual sequence a job really follows; no named competent person for the steps that need one.

Which regulation is a fire and security installer's Method Statement written under?

MHSWR 1999. The full text is on legislation.gov.uk at https://www.legislation.gov.uk/uksi/1999/3242/contents.

How fast can I get a Method Statement?

A couple of minutes. Describe the job, and RAMSReady writes a Method Statement for your exact fire and security installer job live against the correct standard, with a review date and a sign-off/records section.

Not writing this one today?

We will email you a one page overview of what RAMSReady covers, so you have it when you need it.

Want to see how it would work for your firm?

Tell us roughly what you run and who keeps your records, and we will come back to you.

Related guides

Other documents for Fire Alarm & Security Installers

Similar trades

Templates and tools