Risk Assessment · Excavations & Trench Work

Risk Assessment for Excavations & Trench Work

A standalone risk assessment following HSE's 5 steps: who might be harmed and how, and the controls that make the work safe. For excavation, it has to cover trench collapse and burial. It must include hazards specific to the actual task, site and materials. It must also include who might be harmed and how, for each hazard.

A standalone risk assessment following HSE's 5 steps: who might be harmed and how, and the controls that make the work safe. Below: what a Risk Assessment for excavation must contain, why they get rejected, and the hazards it has to cover, or generate one for your exact job in a couple of minutes.

A finished example

Example Risk Assessment from a similar trade (Groundworkers)

We do not have a finished Risk Assessment for excavations & trench work yet, so this one is from groundworkers: the layout, scoring and sign-off are what yours needs, but the hazards and method will be different for your job.

The job it was written for: “Job: excavation, drainage, foundations and external works. Commercial unit, occupied during working hours, 3 operatives, 1 day. Main risks: excavation collapse and buried services; plant and pedestrian interface; manual handling.”. Names and contact details are anonymised.

EXAMPLE

Risk Assessment, Example Groundworker Ltd

FieldDetail
Document titleRisk Assessment: Excavation and foundation works
CompanyExample Groundworker Ltd
AuthorA. Supervisor
Date14 October 2026
VersionV1.0
Review date14 October 2027

Company details

FieldDetail
Company nameExample Groundworker Ltd
Addressto be confirmed
Registration numberto be confirmed
Phoneto be confirmed
Named supervisorA. Supervisor
Insurance valid untilto be confirmed

Task / Activity & Location

Task description: Excavation for drainage and foundations, including use of mechanical plant (excavator, dumper), manual handling of materials, concrete pouring, and general external works.

Location: Unit 4, Example Trading Estate, Exeter EX2 8XX. The site is an occupied commercial unit with ongoing business activities and associated vehicle and pedestrian movements.

Legal basis: This risk assessment is conducted in accordance with The Management of Health and Safety at Work Regulations 1999, Regulation 3. The work falls under The Construction (Design and Management) Regulations 2015.

Hazard Assessment

Note: The control measures listed below are the required standard for this work. The responsible person (A. Supervisor) must ensure they are all implemented and maintained.

HAZARDWHO might be harmed and HOWRISK BEFORE CONTROLS: L × S = Score (Rating)CONTROL MEASURES (what you are already doing PLUS any further action needed, in hierarchy order)RISK AFTER CONTROLS: L × S = Score (Rating)ACTION BY WHOMBY WHENCompleted, date & initials
Collapse of excavation sidesOperatives working in or near the excavation could be buried and crushed by collapsing soil. A cubic metre of soil can weigh over 1.5 tonnes.5 × 5 = 25 (Very High)Engineering controls:<br>1. Excavations deeper than 1.2m will be supported using proprietary trench sheets and props, or battered back to a safe angle determined by a competent person based on ground conditions.<br>2. Support equipment to be on site before excavation begins.<br>3. Excavated spoil and plant to be kept a safe distance from the excavation edge (at least 1m).<br>Administrative controls:<br>4. Daily documented inspections of the excavation by a competent person before entry and after any event likely to affect its stability (e.g. heavy rain).<br>5. Never work ahead of the installed ground support.<br>6. Provide a safe means of access and egress, such as a secured ladder.2 × 5 = 10 (High)A. SupervisorBefore and during works
Contact with underground services (electric, gas, water, telecoms)Operatives could suffer electric shock, burns, or death from striking live cables. Gas leaks could cause fire or explosion. Water main strikes could cause flooding and excavation collapse.5 × 5 = 25 (Very High)Administrative controls:<br>1. Obtain up to date service drawings from all relevant utility providers before work starts.<br>2. Use a Cable Avoidance Tool (CAT) and Signal Generator (Genny) operated by a trained person to scan the entire work area before breaking ground.<br>3. Mark all located services on the ground with paint or stakes.<br>4. Use safe digging techniques (hand tools only) within the immediate vicinity of marked services (typically 0.5m either side).<br>5. Brief all operatives on the location of known services.2 × 5 = 10 (High)A. SupervisorBefore breaking ground
Struck by moving plant (excavator, dumper)Site operatives and members of the public (site is occupied) could be struck, crushed or run over by moving plant, causing serious or fatal injuries.4 × 5 = 20 (Very High)Engineering controls:<br>1. Establish a segregated and barriered work zone using Chapter 8 barriers and appropriate signage to exclude non-essential personnel and the public.<br>2. Ensure all plant is fitted with 360-degree cameras, reversing alarms and flashing beacons.<br>Administrative controls:<br>3. Appoint a competent vehicle banksman for any reversing manoeuvres or operations in congested areas.<br>4. Pedestrians and plant to use separate routes where possible.<br>5. All plant operators to be competent and hold a valid CPCS or NPORS card.<br>6. Ensure high-visibility clothing is worn by all personnel.2 × 4 = 8 (Medium)A. SupervisorBefore and during works
Falls into excavationOperatives or members of the public could fall into the open excavation, causing fractures, head injuries or other serious harm.4 × 4 = 16 (Very High)Engineering controls:<br>1. All open excavations to be protected with rigid barriers (e.g. Chapter 8 barriers) to prevent falls.<br>2. Excavations to be securely covered or barriered off out of working hours.<br>Administrative controls:<br>3. Good housekeeping to be maintained around the excavation edge to prevent trip hazards.<br>4. Adequate lighting to be provided if work continues in poor light.2 × 4 = 8 (Medium)A. SupervisorBefore and during works
Manual handling injuriesOperatives handling heavy or awkward items (kerbs, drainage pipes, bags of cement) could suffer musculoskeletal injuries, such as back strain or sprains.3 × 3 = 9 (Medium)Elimination/Substitution:<br>1. Use mechanical lifting aids (e.g. excavator with certified lifting chains) wherever practicable to move heavy materials, eliminating manual handling.<br>Administrative controls:<br>2. Where manual handling is unavoidable, assess the load and use team lifting for heavy or awkward items. <br>3. Provide manual handling training to all operatives, covering correct lifting techniques.<br>4. Break down loads into smaller, more manageable weights if possible.2 × 2 = 4 (Low)A. SupervisorBefore and during works
Exposure to cement and concrete (alkaline substances)Operatives handling wet cement or concrete can suffer skin burns, dermatitis, or serious eye damage from splashes.3 × 3 = 9 (Medium)Administrative controls:<br>1. Obtain the Safety Data Sheet (SDS) for cement products used. Reduce exposure time.<br>2. Provide welfare facilities with running water, soap and towels for washing.<br>PPE:<br>3. Provide and enforce the use of waterproof gloves (BS EN 374), safety glasses (BS EN 166) and waterproof boots when working with wet concrete or mortar.2 × 2 = 4 (Low)A. SupervisorBefore and during works
Inhalation of dust (respirable crystalline silica - RCS)Operatives cutting, grinding or breaking concrete, stone or kerbs can inhale fine RCS dust, which can lead to silicosis, a serious and incurable lung disease.4 × 4 = 16 (Very High)Engineering controls:<br>1. Use dust suppression techniques at all times when cutting or breaking silica-containing materials. Use water damping or on-tool extraction (LEV).<br>PPE:<br>2. Provide and enforce the use of Respiratory Protective Equipment (RPE) with a minimum assigned protection factor of 20 (e.g. FFP3 mask) for all dust-generating tasks. Face-fit testing is required for tight-fitting masks.2 × 4 = 8 (Medium)A. SupervisorBefore and during works
⛔ STOP, Confirm at site survey: Presence of Asbestos Containing Materials (ACMs)The site is an existing commercial unit. The ground may contain buried asbestos debris or asbestos cement pipes. Disturbing unidentified ACMs can release asbestos fibres, leading to fatal lung diseases.5 × 5 = 25 (Very High)Administrative controls:<br>1. Before any work begins, the Principal Contractor/Client must provide an asbestos survey or management plan for the site, in line with the Control of Asbestos Regulations 2012.<br>2. All groundworkers must receive asbestos awareness training.<br>3. If any material suspected of being an ACM is discovered, all work in the immediate area must stop. The area is to be cordoned off and the supervisor informed immediately. Do not resume work until the material has been identified by a competent person.2 × 5 = 10 (High)A. SupervisorBefore any work starts

Hazardous substances used

The following substances are used or created during the work. A specific COSHH assessment must be completed for each.

SubstanceWhere usedHazardControlsCOSHH assessment ref.
Cement / MortarFoundations, drainage worksAlkaline, skin burns, dermatitis, eye damageWaterproof gloves, eye protection, good hygieneCOSHH-1 (generate)
ConcreteFoundations, finishingAlkaline, skin burns, dermatitis, eye damageWaterproof gloves, eye protection, good hygieneCOSHH-2 (generate)
Respirable Crystalline Silica (RCS) DustCreated when cutting/breaking concrete, kerbs, paving slabsInhalation can cause silicosis, lung cancerWater suppression, on-tool extraction, FFP3 RPECOSHH-3 (generate)
Diesel FuelPowering excavator and dumperFlammable, skin irritant, harmful if ingested or inhaledNo smoking/ignition sources, use of funnel, gloves, good ventilationCOSHH-4 (generate)

Competence and training

RoleRequired competence (cards, tickets, training)Evidence held
All operativesCSCS card; site induction; manual handling training; asbestos awareness trainingto be confirmed by Example Groundworker Ltd
Excavation teamCAT and Genny (cable avoidance tool and signal generator) training; safe digging practiceto be confirmed by Example Groundworker Ltd
Plant operatorsCPCS or NPORS card for the specific excavator and dumper usedto be confirmed by Example Groundworker Ltd
Named first aiderFirst Aid at Work (FAW) or Emergency First Aid at Work (EFAW) certificate, in dateto be confirmed by Example Groundworker Ltd

Emergency arrangements

RoleContact
Site supervisor / emergency contactA. Supervisor, 01283 000000
Named first aiderto be confirmed
First aid kit locationIn site vehicle
Nearest A&E hospitalRoyal Devon and Exeter Hospital, Exeter. confirm before start on site

Rescue plan

A rescue plan is required for any person entering an excavation.

Rescue from excavation collapse or emergency

  • Named rescuer role: All site operatives are designated rescuers, led by the site supervisor. No lone working in or near excavations. At least one person (a 'top person') must remain outside the excavation when someone is inside.
  • Rescue equipment: The following will be kept immediately available at the excavation:<br>- Spare ladders for access/egress.<br>- Mobile phone for emergency services.<br>- First aid kit.
  • Rescue method (in case of collapse or medical emergency):
    1. Raise the alarm immediately. The 'top person' will coordinate the response.
    2. Do not enter a collapsed or unstable excavation. The priority is to prevent further casualties.
    3. Make the immediate area safe. Switch off any nearby plant and secure the excavation edges.
    4. Dial 999 for the emergency services (Fire & Rescue for collapse, Ambulance for injury).
    5. Provide the operator with the precise location: Unit 4, Example Trading Estate, Exeter EX2 8XX, and the nature of the emergency (e.g. 'person trapped in trench collapse').
    6. If a casualty is accessible without entering the trench, provide first aid as trained.
    7. Clear access routes for emergency vehicles and send one person to meet them at the site entrance.
    8. Inform the supervisor, A. Supervisor, immediately.

Significant findings summary

This assessment identifies several high-risk activities associated with the groundworks. The primary risks are trench collapse, contact with buried services, and being struck by moving plant. The controls rely on a combination of engineering solutions (trench support, physical barriers), safe systems of work (daily inspections, safe digging practices, traffic management), and operative competence. The residual risk for several key hazards remains high or medium, requiring strict and continuous supervision by A. Supervisor to ensure all controls are implemented and maintained. The potential presence of asbestos in the ground requires particular caution before work commences.

Risk Matrix Key

LikelihoodDescriptionSeverityDescription
1Very unlikely1Insignificant
2Unlikely2Minor
3Possible3Moderate
4Likely4Major
5Very likely5Catastrophic
RatingRisk LevelAction
16 - 25Very HighUnacceptable, stop work, implement additional controls immediately
10 - 15HighSignificant controls required, senior management attention
5 - 9MediumAdequate controls required, monitor and review
1 - 4LowAcceptable, manage by routine procedures

Review

This risk assessment must be reviewed by 14 October 2027, or immediately if there is any significant change to the work, equipment, location, personnel, or following any accident or near miss.

Declaration and Sign-off

I, the undersigned supervisor, confirm that I have read and understood this Risk Assessment. I will brief all operatives on its contents and ensure the control measures detailed within are implemented, monitored, and maintained for the duration of the works.

NameRoleSignatureDate
A. SupervisorSite Supervisor
Operative
Operative
Operative

What a compliant Risk Assessment must contain

  • Hazards specific to the actual task, site and materials
  • Who might be harmed and how, for each hazard
  • The controls already in place PLUS any further action needed
  • A before/after risk score and a review date

Why a Risk Assessment for excavation gets rejected

  • Copied from a generic example instead of written for the actual task
  • Controls that don't match what the business actually does
  • No record of who does the further actions, or by when
  • An auto-fail hazard (confined space, asbestos, live electrical) wrongly marked 'N/A'

Already have one? Check it against the standard, free.

Paste it below and it is scored the way an inspector would, with the failings that would get it rejected. No sign-up.

Excavations & Trench Work hazards it must cover

Excavation, meaning digging trenches and pits by hand or machine for foundations, drainage and services, brings hazards a Risk Assessment has to address:

  • trench collapse and burial
  • striking buried services (HSG47)
  • falls into excavations
  • plant and vehicles working near the edge
  • flooding and contaminated ground

Generate your Risk Assessment in minutes

Built to the correct published standard for excavation: specific controls, the right legal basis, a review date and a sign-off section you can operate.

Start your Risk Assessment

FAQ

Do you need a Risk Assessment for excavation?

A standalone risk assessment following HSE's 5 steps: who might be harmed and how, and the controls that make the work safe. For excavation, meaning digging trenches and pits by hand or machine for foundations, drainage and services, it is the document a client, principal contractor or inspector expects to see, grounded in MHSWR 1999 reg 3 (HSE): the 5-step method (INDG163).

What must a Risk Assessment for excavation contain?

At minimum: hazards specific to the actual task, site and materials; who might be harmed and how, for each hazard; the controls already in place PLUS any further action needed; A before/after risk score and a review date.

Why does a Risk Assessment for excavation get rejected?

The usual reasons: copied from a generic example instead of written for the actual task; controls that don't match what the business actually does; no record of who does the further actions, or by when; an auto-fail hazard (confined space, asbestos, live electrical) wrongly marked 'N/A'.

Which regulation is a Risk Assessment for excavation written under?

MHSWR 1999. The full text is on legislation.gov.uk at https://www.legislation.gov.uk/uksi/1999/3242/contents.

How fast can I get a Risk Assessment?

A couple of minutes. Describe the job, and RAMSReady writes a Risk Assessment for your exact excavation live against the correct standard, with a review date and a sign-off/records section.

Not writing this one today?

We will email you a one page overview of what RAMSReady covers, so you have it when you need it.

Want to see how it would work for your firm?

Tell us roughly what you run and who keeps your records, and we will come back to you.