A combined Risk Assessment & Method Statement, the site-ready document a principal contractor or client asks for before you start. For solar PV installer work, it has to cover falls from roofs and through fragile roof lights. It must include A hazard table with a likelihood × severity score before and after controls.

A combined Risk Assessment & Method Statement, the site-ready document a principal contractor or client asks for before you start. Below: what a solar PV installer's RAMS must contain, why they get rejected, and the hazards it has to cover, or generate one for your exact job in a couple of minutes.

A finished example

Example RAMS from a similar trade (Roofers)

We do not have a finished RAMS for solar pv installers yet, so this one is from roofers: the layout, scoring and sign-off are what yours needs, but the hazards and method will be different for your job.

The job it was written for: “Strip and re-felt a flat garage roof on a semi-detached house, 3 lads, one day, bitumen torch-on felt, access by ladder and tower, skip on the drive”. Names and contact details are anonymised.

EXAMPLE

RAMS - Flat Garage Roof Strip and Re-felt - Example Roofer Ltd, 14 Orchard Close, Exeter EX4 2AB


Document Title: Risk Assessment and Method Statement - Flat Garage Roof Strip and Re-felt Company: Example Roofer Ltd Author / Supervisor: A. Supervisor Version: V1.0 Date of Assessment: 13 October 2026 Review Date: 13 October 2027 Emergency Contact: A. Supervisor, 01283 000000 Legal Basis: MHSWR 1999 reg 3 (suitable and sufficient risk assessment; significant findings recorded under reg 3(6)); WAH 2005; CDM 2015 dutyholder roles noted where applicable

NOTE TO RESPONSIBLE PERSON: The controls in Section 4 are recommended control measures. You must confirm which are in place and which still require action before work begins. Use the "Completed - date and initials" column to record this. Do not allow work to start until all controls are confirmed or an alternative of equivalent effect is documented.


Project / Job Information

FieldDetail
Site Address14 Orchard Close, Exeter EX4 2AB
Client / Principal ContractorExample Client
ContractorExample Roofer Ltd
SupervisorA. Supervisor
Emergency ContactA. Supervisor, 01283 000000
Start Date13 October 2026
Estimated Duration1 day
Number of Operatives3
CDM RoleContractor (confirm with Example Client whether a construction phase plan is required under CDM 2015)

Scope of Works

Strip all existing felt layers from a single-storey flat garage roof at 14 Orchard Close, Exeter. Roof height is approximately 2.8 m above ground level. Dispose of stripped material into a skip positioned on the drive. Apply new bitumen torch-on felt system (typically cap sheet and base layer) using a propane torch. Access to the roof surface is by tied aluminium ladder. Working platform on the roof is provided by an alloy tower scaffold with guardrails. Three operatives; one working day.


Hazard Identification Table

Risk Score = Likelihood (L) × Severity (S) Ratings: 1 to 4 Low | 5 to 9 Medium | 10 to 15 High | 16 to 25 Very High

#HazardWorst-Case OutcomeWho Is at RiskLSInitial Score (Rating)Recommended Control Measures - confirm/implement on siteLSResidual Score (Rating)Completed - date and initials
1Fall from roof edge or through roof surface (2.8 m working height)Fatal or major injury (fractured skull, spinal injury)All 3 operatives3515 (High)(a) Erect alloy tower to manufacturer's instructions and PASMA guidance before anyone steps onto the roof surface; tower must reach at least 1 m above roof level with full guardrail (top rail, mid-rail, toe-board) on all open sides. (b) Work from the tower platform when at the roof perimeter; do not lean out beyond the guardrail. (c) Access ladder tied at the top; foot held by a second person during ascent/descent. (d) Pre-inspect roof deck for soft or rotten areas before full loading; probe suspect boards with a bar tool and do not stand on any area not confirmed sound. (e) Buddy system: no operative works alone at roof level. (f) Exclusion zone (minimum 2 m) below and around the ladder and tower, marked with cones and barrier tape.2510 (High)
2Person or material struck by falling objects (stripped felt, batten offcuts, tools)Head injury, fracturesOperative below, householder, passing members of public3412 (High)(a) Establish exclusion zone on the drive around the skip and below the working area; use cones and barrier tape before work starts. (b) Brief the householder (Example Client / occupier) to keep clear; ask that doors and windows on the garage side remain closed during the strip. (c) Neighbours already notified - confirm on the morning of the job that they are aware. (d) All operatives wearing hard hats at roof level and on the ground below. (e) Stripped felt to be lowered or slid into the skip in controlled sections; do not throw material. (f) Tools not in use to be placed in a bucket or tool bag on the platform - not left loose on the roof surface.248 (Medium)
3Fire from propane torch-on felt operations (uPVC fascias, gutters, adjacent combustibles)Structural fire, burn injuries, damage to neighbouring propertyAll 3 operatives, neighbour, householder3515 (High)(a) Hot-works permit to be completed and signed by A. Supervisor before the torch is lit each time. (b) A. Supervisor (10 years' experience with bitumen torch) to operate the torch only; no other operative to use the torch without documented authority. (c) Remove or protect uPVC fascias and gutters directly beneath the torch work area with fire-resistant board or mineral-wool mat before torching begins; inspect protection is in position before each torch session. (d) Propane cylinder to be positioned upright on a stable surface at ground level or on the tower base board, secured against tip; keep a minimum 3 m clear zone around the cylinder. (e) A 9-litre water or 6 kg dry-powder fire extinguisher to be present on the roof platform and a second extinguisher at ground level before torch is lit. (f) Fire watch: a second operative to watch for smouldering at all times while the torch is in use; torch not to be laid down lit. (g) Post-work fire watch of at least 60 minutes after the torch is finally extinguished; check roof deck, fascias and gutters for heat or smoke at the end of the fire-watch period. (h) Torch head to be quenched and cylinder valve closed when not in active use. (i) Mobile phone with network signal available on site at all times (emergency contact A. Supervisor, 01283 000000; 999 for fire).2510 (High)
4Manual handling of heavy materials (rolled bitumen felt, stripped felt bundles, skip loading)Musculoskeletal injury (back, shoulder)All 3 operatives339 (Medium)(a) Rolled felt to be assessed for weight before lifting; rolls over 25 kg to be carried by two persons. (b) Mechanical aid (sack truck or wheel-barrow) to be used to transport rolls from the delivery point to the foot of the ladder where practicable. (c) Felt rolls to be passed up the ladder in stages - one person on the ladder, one person steadying the roll at the base; do not carry a roll single-handed up the ladder. (d) Strip felt into manageable sections; bag or bundle before throwing or sliding into the skip. (e) Pre-task briefing to cover correct lifting posture; operative to stop and report any back or shoulder pain immediately.236 (Medium)
5Contact with hot bitumen / torch flame (burns during torch-on application)Burn injuries (hands, face, lower limbs)Torch operator (A. Supervisor) and nearby operatives248 (Medium)(a) Torch operator to wear heat-resistant gloves, leather or flame-retardant trousers, and leather work boots - no synthetic fabrics near the torch. (b) Direct the torch flame away from hands and feet at all times; work in short forward passes. (c) No other operative to stand within 1.5 m of the torch head. (d) Burns first-aid kit (including a burn dressing/gel and sterile wound cover) to be in the site first-aid kit on site. (e) If a burn occurs: cool with running water for 20 minutes; do not apply creams or burst blisters; call 999 if significant.236 (Medium)
6Propane cylinder - leakage, fire, or explosionExplosion / serious burnsAll 3 operatives, householder, members of public2510 (High)(a) Inspect cylinder, hose and torch head for damage before use; check hose connections with leak-detection spray (not a naked flame). (b) Cylinder to remain upright and secured; no storage in an enclosed space (garage interior or vehicle). (c) No smoking within 5 m of the cylinder. (d) If a leak is suspected: close the cylinder valve immediately, move personnel clear, ventilate, and do not re-use until inspected by a competent gas engineer. (e) Emergency contact A. Supervisor, 01283 000000; 999 for fire or explosion.155 (Medium)
7Slips, trips on the roof surface (debris, wet felt, tool bags)Falls on the same level or over the edgeAll 3 operatives339 (Medium)(a) Clear stripped felt and debris progressively into the skip; do not allow waste to accumulate on the roof surface. (b) Operatives to wear safety boots with slip-resistant soles suitable for roofing. (c) If the roof surface is wet, assess before work; if felt or deck is slippery and guardrails do not fully contain the slip risk, defer until conditions improve or increase fall-arrest measures. (d) Tool bags and equipment placed on the tower platform, not loose on the roof.236 (Medium)
8Skip on the drive - struck by reversing vehicle, obstruction of pavement / footpathCrush injury, pedestrian accidentOperatives, householder, pedestrians248 (Medium)(a) Skip placed entirely on the private drive within the property boundary where possible; confirm skip hire company has placed it to the client's confirmation. (b) If the skip overhangs the footpath, a skip licence from Exeter City Council must be in place before delivery; confirm with Example Client. (c) Hi-visibility markers (cones, hazard tape) around the skip. (d) When the skip lorry is reversing onto or off the drive, a banksman is to be in place; no other person to be in the reversing path.236 (Medium)
9⛔ STOP - CONFIRM AT SITE SURVEY: Asbestos in existing roof build-up or soffit boardsInhalation of asbestos fibres; mesothelioma, lung cancerAll 3 operatives, householder, neighbours4520 (Very High)The garage is part of a semi-detached house. If the property was constructed or last re-roofed before the year 2000, asbestos-containing materials (ACMs) may be present in the existing felt layers, bonding compound, roof deck boards, or soffit. (a) Before work starts, check the property's asbestos register or refurbishment/demolition survey (Control of Asbestos Regulations 2012 reg 4/5). If no survey exists, commission one before disturbing any existing roof material. (b) If ACMs are confirmed or cannot be ruled out: do not proceed with the strip until materials are assessed, sampled, and managed or removed by a licensed/competent asbestos contractor as required by CAR 2012. (c) If the roof is confirmed free of ACMs by a competent surveyor, remove this ⛔ block and retain the survey report with this RAMS. Do not assume absence on the basis of visual inspection alone.155 (Medium - only if survey confirms absence)
10Extreme weather - wind on elevated platform, cold/wet conditionsTower instability; operative hypothermia or reduced gripAll 3 operatives248 (Medium)(a) Check forecast before work begins; do not work on the tower if wind speed exceeds the tower manufacturer's rated maximum (typically 17 mph / Beaufort Force 5 for an untied tower at this height). (b) In October at Exeter, temperatures may be low and surfaces may be wet in the morning; defer start until the roof surface is dry enough to work safely. (c) Operatives to wear appropriate PPE for cold/wet weather; layer clothing as needed. (d) Welfare: hot drinks and rest breaks available (see Section 9).236 (Medium)

Method Statement - Step-by-Step Safe Sequence of Work

  1. Pre-start site survey (all operatives, 07:30 to 08:00). A. Supervisor to walk the site before any equipment is unloaded. Confirm: roof surface condition and deck soundness; presence or absence of asbestos-containing materials (if survey not already completed, work must stop at this point - see Hazard 9). Note proximity of uPVC fascias and gutters on all four sides of the garage. Confirm skip is positioned correctly on the drive and council licence is in place if required. Check weather forecast; wind speed must be within tower manufacturer's limits before proceeding.

  2. Exclusion zone and signage. Place cones and barrier tape in a minimum 2 m zone below and around the working face of the garage and around the skip. Brief the householder or occupier to keep clear of the zone; confirm neighbours are aware as pre-notified.

  3. Alloy tower erection. Erect the alloy tower scaffold to the manufacturer's instructions and in accordance with PASMA guidance. Tower must be erected by a PASMA-trained operative. Confirm: all frames, braces, and locking pins are engaged; base plates or castors are locked and on firm, level ground; top guardrail, mid-rail, and toe-boards are fitted on all open sides; working platform height gives access to the roof level without the need to climb above the guardrail.

  4. Ladder tie. Position the aluminium ladder against the roof edge at a 1-in-4 angle; tie the top of the ladder securely to a fixed anchor point (roof edge or fascia board of sufficient strength). Foot of the ladder to be held by a second operative during all ascents and descents.

  5. Material delivery to roof level. Carry bitumen felt rolls and equipment to roof level. Rolls above 25 kg: two-person carry at ground level; pass up the ladder one roll at a time with one operative on the ladder and one person stabilising at the base. Place materials on the tower platform, not loose on the roof surface.

  6. Hot-works permit. Before the propane torch is connected, A. Supervisor to complete and sign the hot-works permit for this site and this day. Confirm: both fire extinguishers are in position (one on the tower platform, one at ground level); fire-watch operative is briefed and in position; uPVC fascias and gutters are protected with fire-resistant board or mineral-wool mat below the torch work area.

  7. Propane cylinder inspection and connection. A. Supervisor to inspect the cylinder, hose, and torch head for damage or wear. Connect the hose; check all connections using leak-detection spray. Confirm the cylinder is upright, secured, and positioned at least 3 m from ignition sources. Record the cylinder batch number on the hot-works permit.

  8. Existing felt strip. Working from the tower platform at the perimeter and stepping carefully onto confirmed-sound deck boards for the central areas, strip the existing felt using a roofing bolster/spade bar. Do not use the torch during the strip. Cut stripped felt into manageable sections; slide or carry sections to the skip. Do not throw material over the edge; lower or slide in a controlled manner. Clear debris progressively to keep the working surface clear.

  9. Deck inspection and preparation. Inspect the exposed roof deck for rot, delamination, or soft spots. Any boards requiring replacement must be replaced before felt is applied. Sweep the deck clean of all loose debris, dust, and fastener protections.

  10. Base layer torch-on application. A. Supervisor operates the propane torch only. Direct the flame onto the underside of the base-layer felt, rolling it out forward in short controlled passes. Fire-watch operative to observe the fascias, gutters, and deck at all times and call "STOP" immediately on any sign of smoke or smouldering. Torch not to be laid down lit; quench the head and close the cylinder valve whenever the torch is set down.

  11. Cap sheet torch-on application. Apply the cap sheet in the same sequence, lapping joints in accordance with the felt manufacturer's specification (confirm lap dimension from the product data sheet before starting). Press all laps firmly with a roller. Inspect joints after each section.

  12. Ongoing fire watch. Throughout all torch work and for a minimum of 60 minutes after the torch is finally extinguished, the designated fire-watch operative monitors the roof surface, fascias, gutters, and underside of the eaves for heat or smoke. The fire-watch must not be abandoned early. A. Supervisor signs off the fire watch on the hot-works permit at the end of the observation period.

  13. Cylinder and torch make-safe. Close the cylinder valve; purge the hose by operating the torch until the flame dies. Disconnect the hose. Cap the cylinder. Return the cylinder to the vehicle or a ventilated outdoor storage area; do not store in the garage or a closed vehicle.

  14. Tower strike and ladder removal. Once the roof is complete and the fire-watch period has ended, lower all tools and remaining materials from the roof before dismantling the tower. Strike the tower in reverse order of erection (PASMA guidance). Remove the ladder last.

  15. Clear-up and site check. Remove all waste from the drive and ensure the skip is loaded safely. Retrieve all barrier tape, cones, and signage. Walk the site with A. Supervisor to confirm: no materials left on the roof; no damage to fascias, gutters, or adjacent property; fire watch completed and signed off; site is clean and secure. A. Supervisor signs the RAMS sign-off table.


PPE Requirements

ItemStandardNotes
Safety helmetBS EN 397Worn by all operatives at all times on site
High-visibility vest or jacketBS EN ISO 20471Worn when near vehicle movements (skip lorry)
Safety boots (slip-resistant sole)BS EN ISO 20345Roofing-appropriate sole profile
Safety glasses / gogglesBS EN 166During felt stripping; debris and dust risk
Heat-resistant gloves (leather)BS EN 407Torch operator and felt-rolling work
General-purpose work glovesBS EN 388Stripping and handling felt
Knee padsN/ADuring kneeling work on the deck
Dust mask (FFP2 minimum)BS EN 149During stripping of old felt (dust and degraded bitumen particulates)
Flame-retardant or leather trousersN/ATorch operator; no synthetic fabrics

Note: If the asbestos survey (Hazard 9) identifies any ACMs, the above RPE specification is insufficient. Suitable RPE for asbestos work (minimum FFP3 or powered air-purifying) and all other CAR 2012 controls will be required before further work.


Emergency Procedures

Site Emergency Contact: A. Supervisor - A. Supervisor, 01283 000000 Emergency Services: 999

First Aid

At least one operative must hold a current First Aid at Work or Emergency First Aid at Work certificate. A first-aid kit including burn dressings and gel must be present on site before work starts. Nearest A&E: Royal Devon and Exeter Hospital, Barrack Road, Exeter EX2 5DW (approximately 1.5 miles from site).

Burns

Cool with running water for a minimum of 20 minutes. Do not apply creams, ointments, or adhesive dressings directly to a burn. Call 999 for significant burns. RIDDOR reporting required for any burn requiring hospital treatment (RIDDOR 2013).

Fire

On discovery of fire: shout "FIRE", clear all operatives from the roof immediately using the ladder, call 999. Do not attempt to fight a fire that is beyond the incipient stage. Confirm the householder and any occupants are clear of the building. Meet emergency services at the site entrance and brief them on the propane cylinder location.

Fall from Height

Do not move a person who has fallen from height unless they are in immediate danger. Call 999. Notify A. Supervisor (A. Supervisor, 01283 000000). RIDDOR reporting is required for any over-7-day injury, hospital admission, or specified injury.

Propane Leak

Close the cylinder valve immediately. Move all personnel upwind and clear of the area. Do not operate any switches or ignition sources. Call 999 if a leak cannot be stopped by closing the valve.

Asbestos Discovery

If material suspected to be asbestos is encountered during stripping, stop work immediately, move operatives downwind, seal the area, and contact A. Supervisor. Do not resume work until a competent asbestos surveyor has assessed the material.


Environmental Considerations

  • Stripped bitumen felt is hazardous waste and must not be mixed with general domestic waste in the skip. Confirm with the skip hire company that the skip is licensed to accept bitumen roofing waste; retain the waste transfer note.
  • Bitumen drips or residue on the drive or paths: protect the drive surface below the working area with polythene sheeting before torch work begins. Clean up any bitumen with an appropriate solvent or mechanical means; do not wash into drains.
  • Propane cylinder: return empty or part-full cylinders to the supplier. Never dispose of in domestic waste.
  • Neighbours' property: any debris reaching a neighbouring garden or driveway to be removed immediately and the neighbour informed.

Welfare

RequirementProvision
Toilets and washing facilitiesConfirm with Example Client / householder that access to toilet and hand-washing facilities at 14 Orchard Close is agreed before work starts; or provide a welfare van/facilities on the drive.
Drinking waterOperatives to bring adequate drinking water; hot drinks via flask or nearby café.
Rest areaWelfare van on site, or the client's agreed provision. Not to be the garage interior, as the garage is a live work area.
First aidFirst-aid kit on site; trained first-aider confirmed before work starts.

Risk Matrix Key

Likelihood1 Insignificant2 Minor3 Moderate4 Major5 Catastrophic
1 Very unlikely1 Low2 Low3 Low4 Low5 Medium
2 Unlikely2 Low4 Low6 Medium8 Medium10 High
3 Possible3 Low6 Medium9 Medium12 High15 High
4 Likely4 Low8 Medium12 High16 Very High20 Very High
5 Very likely5 Medium10 High15 High20 Very High25 Very High
ScoreRatingAction
1 to 4LowAcceptable - manage by routine procedures
5 to 9MediumAdequate controls required - monitor and review
10 to 15HighSignificant controls required - senior management attention
16 to 25Very HighUnacceptable - stop work, implement additional controls immediately

Sign-off and Declaration

Responsible Person Declaration: I confirm that I have reviewed this RAMS, that the recommended controls have been confirmed or implemented on site, that all operatives have read and understood this document, and that work will not commence until all outstanding actions are resolved.

NameRoleSignatureDate
A. SupervisorSupervisor / Responsible Person

Operative Read and Sign - confirm understanding before work begins:

NameSignatureDate

Outstanding actions (if any) confirmed resolved before work start:

ActionResponsibleCompleted - date and initials
Asbestos refurbishment/demolition survey obtained and reviewedA. Supervisor
Hot-works permit completed and signedA. Supervisor
PASMA-trained operative confirmed for tower erectionA. Supervisor
Skip licence confirmed with Exeter City Council (if skip overhangs footpath)A. Supervisor / Example Client
Welfare provision confirmed with householder / Example ClientA. Supervisor
Fire-watch operative briefed and confirmedA. Supervisor
First-aider confirmed on site with valid certificateA. Supervisor

This document discharges the recording duty under MHSWR 1999 reg 3(6) and feeds into the construction phase plan as required under CDM 2015. It must be reviewed within 12 months of the assessment date (by 13 October 2027) or sooner if there is a significant change to the work, site conditions, or personnel.

What a compliant RAMS must contain

  • A hazard table with a likelihood × severity score before and after controls
  • Controls in the correct hierarchy (eliminate → substitute → engineering → admin → PPE last)
  • A numbered, step-by-step method statement for the actual task
  • PPE to BS EN standards, emergency arrangements, and an operative sign-off

Why a solar PV installer's RAMS gets rejected

  • Residual risk dropped from high to low on PPE or 'competent operatives' alone
  • Generic hazards that could apply to any job
  • No method statement, or one too vague to follow on site
  • The wrong legal basis cited, such as CDM 2015 named for work that is not construction

Already have one? Check it against the standard, free.

Paste it below and it is scored the way an inspector would, with the failings that would get it rejected. No sign-up.

Solar PV Installers hazards it must cover

Typical solar PV installer work, meaning roof-mounted and ground-mounted PV arrays, inverters, battery storage and DNO connections, brings hazards a RAMS has to address:

  • falls from roofs and through fragile roof lights
  • DC electric shock (panels are live in daylight and cannot be switched off)
  • manual handling of panels in wind
  • arc flash on inverter and battery work
  • fire risk from battery storage

Generate your RAMS in minutes

Built to the correct published standard for a solar PV installer: specific controls, the right legal basis, a review date and a sign-off section you can operate.

Start your RAMS

FAQ

Do solar pv installers legally need a RAMS?

A combined Risk Assessment & Method Statement, the site-ready document a principal contractor or client asks for before you start. For solar PV installer work, meaning roof-mounted and ground-mounted PV arrays, inverters, battery storage and DNO connections, it is the document a client, principal contractor or inspector expects to see, grounded in MHSWR 1999 reg 3 (HSE): the combined risk assessment + method statement contractors submit.

What must a solar PV installer's RAMS contain?

At minimum: A hazard table with a likelihood × severity score before and after controls; controls in the correct hierarchy (eliminate → substitute → engineering → admin → PPE last); A numbered, step-by-step method statement for the actual task; PPE to BS EN standards, emergency arrangements, and an operative sign-off.

Why does a solar PV installer's RAMS get rejected?

The usual reasons: residual risk dropped from high to low on PPE or 'competent operatives' alone; generic hazards that could apply to any job; no method statement, or one too vague to follow on site; the wrong legal basis cited, such as CDM 2015 named for work that is not construction.

Which regulation is a solar PV installer's RAMS written under?

MHSWR 1999. The full text is on legislation.gov.uk at https://www.legislation.gov.uk/uksi/1999/3242/contents.

How fast can I get a RAMS?

A couple of minutes. Describe the job, and RAMSReady writes a RAMS for your exact solar PV installer job live against the correct standard, with a review date and a sign-off/records section.

Not writing this one today?

We will email you a one page overview of what RAMSReady covers, so you have it when you need it.

Want to see how it would work for your firm?

Tell us roughly what you run and who keeps your records, and we will come back to you.

Related guides

Other documents for Solar PV Installers

Similar trades

Templates and tools