RAMS for Tree Surgeons & Arborists

A combined Risk Assessment & Method Statement, the site-ready document a principal contractor or client asks for before you start. For tree surgeon work, it has to cover falls from height during climbing and aerial rescue. It must include A hazard table with a likelihood × severity score before and after controls.

A combined Risk Assessment & Method Statement, the site-ready document a principal contractor or client asks for before you start. Below: what a tree surgeon's RAMS must contain, why they get rejected, and the hazards it has to cover, or generate one for your exact job in a couple of minutes.

A finished example

Example RAMS from a similar trade (Scaffolders)

We do not have a finished RAMS for tree surgeons & arborists yet, so this one is from scaffolders: the layout, scoring and sign-off are what yours needs, but the hazards and method will be different for your job.

The job it was written for: “Job: erecting, altering and dismantling access scaffold. Commercial unit, occupied during working hours, 4 operatives, 1 day. Main risks: falls from height during erection; falling materials and tools; manual handling of tube and fittings.”. Names and contact details are anonymised.

EXAMPLE

Risk Assessment & Method Statement, Scaffolding

FieldDetail
Document TitleRAMS, Erection, Alteration & Dismantling of Access Scaffold
CompanyExample Scaffolder Ltd
AuthorA. Supervisor
Date14 October 2026
VersionV1.0
Review Date14 October 2027

Company details

FieldDetail
Company nameExample Scaffolder Ltd
Addressto be confirmed
Registration numberto be confirmed
Phoneto be confirmed
Named supervisorA. Supervisor
Insurance valid untilto be confirmed

Project / Job information

FieldDetail
Site addressUnit 4, Example Trading Estate, Exeter EX2 8XX
ClientExample Client
Principal contractorExample Client
Start date14 October 2026
Planned duration1 day

This Risk Assessment and Method Statement is produced in accordance with the Management of Health and Safety at Work Regulations 1999, Regulation 3. The significant findings are recorded here. For projects falling under the Construction (Design and Management) Regulations 2015, this document will inform the construction phase plan.

Scope of works

Erection, alteration, and dismantling of a tube and fitting access scaffold to provide safe working access at Unit 4, Example Trading Estate. The work will be undertaken by a team of four operatives while the commercial unit remains occupied. The work includes setting out, base-out, erection of lifts, tying in, boarding, installation of edge protection, handover, subsequent alteration if required, and final dismantling.

Hazard identification table

HAZARDRISK / WORST-CASE OUTCOMEWHO IS AT RISKRISK BEFORE CONTROLS: L × S = Score (Rating)CONTROL MEASURES (in hierarchy order, specific and measurable)RISK AFTER CONTROLS: L × S = Score (Rating)
Working at height, fall of personFall from an incomplete scaffold platform or during access, leading to multiple serious injuries or death.Scaffolders, other site workers5 × 5 = 25 (Very High)1. Engineering: Scaffold to be erected using a safe method that provides collective fall protection at all times, such as the 'Scaffolders' Safe Zone' method using advance guardrails (in accordance with NASC guidance SG4:15).<br>2. Admin: Scaffolders to be CISRS-qualified for the type of scaffold being erected and trained in SG4:15. Work supervised by a competent CISRS Scaffolder/Supervisor. No work on incomplete, unguarded platforms.<br>3. PPE: Personal fall arrest equipment (harness and lanyard) to be worn and used only as a last resort where collective controls are not practicable. Harnesses to be inspected pre-use. Rescue plan in place.3 × 4 = 12 (High)
Falling materials or toolsScaffold tubes, fittings, or tools dropped from height, causing severe head injury or death to persons below.Public, client staff, other contractors5 × 5 = 25 (Very High)1. Engineering: Establish a restricted work zone directly below the scaffolding area using physical barriers (e.g., Chapter 8 barriers) and clear warning signs. No unauthorised persons to enter.<br>2. Admin: Do not throw materials from the scaffold. Pass or hoist materials in a controlled manner (e.g., gin wheel and rope, or pass hand-to-hand). Tools to be kept in tool bags attached to the belt. Good housekeeping maintained on platforms.<br>3. PPE: All operatives on site to wear hard hats (BS EN 397).2 × 4 = 8 (Medium)
Manual handlingMusculoskeletal injuries (sprains, strains, back injury) from lifting, carrying, and passing heavy or awkward scaffold tubes and boards.Scaffolders4 × 3 = 12 (High)1. Admin: Use correct kinetic lifting techniques (bend knees, keep back straight). Use team lifting for long or heavy components. Break down loads into manageable weights where possible. Ensure clear, level access routes for carrying materials. Rotate tasks to avoid repetitive strain. Operatives trained in manual handling.2 × 3 = 6 (Medium)
Slips, trips and falls on same levelSlips on wet surfaces or trips over poorly stored materials, causing fractures or other impact injuries.Scaffolders, client staff, public3 × 3 = 9 (Medium)1. Admin: Maintain good housekeeping at all times. Stack materials in designated, stable stacks away from pedestrian routes. Keep work area tidy and free from offcuts and discarded fittings. Wear safety boots (BS EN ISO 20345) with good grip. Clean up any spills immediately.2 × 2 = 4 (Low)
Contact with live electrical servicesElectrocution or severe burns from contact with overhead power lines or fixed electrical services on the building facade.Scaffolders4 × 5 = 20 (Very High)1. Eliminate/Admin: Identify all electrical services in the work area during site survey (overhead lines, cables, lighting, CCTV). Maintain safe clearance distances as per HSE guidance GS6. If minimum distances cannot be maintained, services must be de-energised and proven dead by a qualified electrician before work starts. Scaffold design to avoid proximity to services.2 × 5 = 10 (High)
Disturbance of asbestos containing materials (ACMs)⛔ STOP, CONFIRM AT SITE SURVEY: Inhalation of asbestos fibres if the building fabric (pre-2000) is drilled for ties, causing incurable cancer (mesothelioma).Scaffolders, building occupants5 × 5 = 25 (Very High)1. Admin: WORK MUST NOT START until the client provides an up-to-date Asbestos Refurbishment & Demolition Survey for the areas to be disturbed. If no survey exists, one must be commissioned. If ACMs are identified where ties are required, a licensed asbestos contractor must be engaged to manage or remove them before scaffolding work proceeds. The Control of Asbestos Regulations 2012 apply.1 × 5 = 5 (Medium)
Public interfaceUnauthorised access to the scaffold, or collision between site vehicles/operatives and members of the public or client staff.Public, client staff3 × 4 = 12 (High)1. Engineering: Erection/dismantling zone to be segregated from public and building occupants with physical barriers and signage. Ground floor lifts to be boarded at the earliest opportunity to prevent climbing. Ladders to be removed or locked at the end of each shift to prevent unauthorised access.<br>2. Admin: Appoint a banksman for all vehicle movements. Maintain segregation at all times.2 × 4 = 8 (Medium)

Method statement

Note: All controls identified in the risk assessment table above must be implemented. The site supervisor is responsible for confirming controls are in place before work starts.

1. Pre-start briefing and checks

  1. All operatives to sign onto this RAMS after a pre-start briefing delivered by the supervisor, confirming understanding of the risks and controls.
  2. Inspect all equipment before use, including scaffold components, vehicle, hoist, and PPE. Any defective equipment is to be quarantined and not used.
  3. Establish a segregated work zone around the scaffold footprint using barriers and warning signs. Ensure public and unauthorised site staff cannot enter the area.
  4. Confirm location of site welfare facilities and emergency arrangements.

2. Scaffold erection

  1. Unload materials from the vehicle safely, stacking them neatly within the designated lay-down area, away from access routes.
  2. Set out sole boards and base plates on firm, level ground.
  3. Erect the first lift of standards, ledgers and transoms, ensuring the structure is level and plumb.
  4. Install the first working platform. Access to this level will be via a secured ladder.
  5. Erect subsequent lifts using the 'Scaffolders' Safe Zone' advance guardrail method (SG4:15). A temporary guardrail is created from the level below, providing collective fall protection for operatives placing the next lift of boards.
  6. At required intervals (typically every other lift), tie the scaffold into the building's structural frame. STOP: Confirm from the asbestos survey that tie-in locations are free from ACMs before drilling.
  7. Continue erecting lifts until the required height is reached, ensuring all working platforms are fully boarded, with double guardrails and toeboards installed.
  8. Install required ladder access points, ensuring they are secure and extend 1 metre above the landing platform.
  9. Once complete, the supervisor will inspect the scaffold against the design/specification and TG20:21 compliance sheet. A handover certificate will be issued to the client.

3. Alterations

  1. Any required alterations to the scaffold must only be carried out by a competent CISRS scaffolder.
  2. The area below the alteration work must be segregated.
  3. No unauthorised alterations are permitted.

4. Dismantling

  1. Dismantling will be carried out in the reverse order to erection.
  2. Ensure the area below is clear and segregated.
  3. Never remove ties or structural components that would compromise the stability of the remaining structure.
  4. Lower components in a controlled manner using a gin wheel and rope or by passing hand-to-hand. Do not throw materials to the ground.
  5. On completion, clear the work area of all materials and debris.
  6. The supervisor will conduct a final inspection to ensure the area is left safe and tidy.

Hazardous substances used

SubstanceWhere usedHazardControlsCOSHH assessment ref.
Silica dustMay be created if drilling into concrete/masonry for ties.Inhalation can cause silicosis, a serious lung disease.Use of drills with on-tool extraction (LEV). RPE (FFP3 mask). Dampen down dust where possible.COSHH-1 (generate)
General dust and debrisErection and dismantling activities.Eye and respiratory irritation.Safety glasses (BS EN 166). RPE (FFP2 mask) if dust levels are high. Good housekeeping.COSHH-2 (generate)

Competence and training

RoleRequired competence (cards, tickets, training)Evidence held
All operativesCSCS card; site induction; manual handling trainingto be confirmed by Example Scaffolder Ltd
ScaffoldersCISRS Scaffolder/Advanced Scaffolder Card as appropriate for the workto be confirmed by Example Scaffolder Ltd
Operatives working at heightWorking at height training; SG4:15 awareness; harness inspection and useto be confirmed by Example Scaffolder Ltd
Named first aiderFirst Aid at Work (FAW) certificate, in dateto be confirmed by Example Scaffolder Ltd

PPE requirements

ItemStandard
Hard hatBS EN 397
High-visibility clothingBS EN ISO 20471
Safety boots with toe and mid-sole protectionBS EN ISO 20345
Safety glasses / gogglesBS EN 166
Protective gloves (cut-resistant)BS EN 388
Fall arrest harness and energy-absorbing lanyardBS EN 361, BS EN 355

Emergency arrangements

ItemDetail
Site supervisorA. Supervisor
Emergency contactA. Supervisor, 01283 000000
First aiderto be confirmed
First aid kit locationIn site vehicle
Fire assembly pointAs designated by the site's fire plan, confirm during induction
Nearest A&E hospitalRoyal Devon and Exeter Hospital, confirm before start on site
Emergency procedureIn case of serious injury: 1. Stop work. 2. Make the area safe. 3. Call emergency services on 999. 4. Inform the supervisor immediately.
Spill procedureN/A for this activity.

Rescue plan

A rescue plan is required for work at height. In the event of a fall where an operative is suspended in a harness, rescue must be immediate.

  • Rescuer role: The remaining members of the scaffold team on site will form the rescue party, led by the site supervisor. All are trained in harness use.
  • Rescue equipment: A dedicated pre-packed rescue kit will be kept on site. Additional ladders and a MEWP (if on site) may be used.
  • Rescue method:
    1. The primary method is to rescue the casualty from a position of safety (e.g., a completed scaffold platform or from a MEWP).
    2. If possible, the casualty will be raised or lowered to the nearest safe platform using the rescue kit.
    3. The conscious casualty should be instructed to push up with their legs against any available surface to relieve pressure.
    4. The aim is to get the casualty to a safe place within 10 minutes.
  • Suspension trauma: A person suspended in a harness can lose consciousness. The rescue must be performed as quickly as possible. The ambulance service must be called immediately and informed that the casualty has been suspended in a harness.
  • Emergency services call: The site supervisor will dial 999, giving the site address (Unit 4, Example Trading Estate, Exeter EX2 8XX), nature of the incident, and access point. A person will be sent to the site entrance to meet the ambulance.

Environmental considerations

  • All waste materials will be removed from site and disposed of by a licensed waste carrier.
  • Noise will be kept to a minimum, particularly as the building is occupied.
  • Work will be planned to minimise disruption to the client's operations.

Welfare (construction only)

Welfare facilities, including toilets, washing facilities, rest area and drinking water, will be provided by the client as agreed. To be confirmed during site induction.

Risk matrix key & sign-off

The risk rating has been calculated using the following 5x5 matrix.

Likelihood1 (Very unlikely)2 (Unlikely)3 (Possible)4 (Likely)5 (Very likely)
5 (Catastrophic)510152025
4 (Major)48121620
3 (Moderate)3691215
2 (Minor)246810
1 (Insignificant)12345
RatingRisk LevelAction
1-4LowAcceptable, manage by routine procedures
5-9MediumAdequate controls required, monitor and review
10-15HighSignificant controls required, senior management attention
16-25Very HighUnacceptable, stop work, implement additional controls immediately

Declaration and Operative Sign-off

I have read and understood this Risk Assessment and Method Statement. I agree to work in accordance with its requirements and controls.

NameRoleSignatureDate

What a compliant RAMS must contain

  • A hazard table with a likelihood × severity score before and after controls
  • Controls in the correct hierarchy (eliminate → substitute → engineering → admin → PPE last)
  • A numbered, step-by-step method statement for the actual task
  • PPE to BS EN standards, emergency arrangements, and an operative sign-off

Why a tree surgeon's RAMS gets rejected

  • Residual risk dropped from high to low on PPE or 'competent operatives' alone
  • Generic hazards that could apply to any job
  • No method statement, or one too vague to follow on site
  • The wrong legal basis cited, such as CDM 2015 named for work that is not construction

Already have one? Check it against the standard, free.

Paste it below and it is scored the way an inspector would, with the failings that would get it rejected. No sign-up.

Tree Surgeons & Arborists hazards it must cover

Typical tree surgeon work, meaning felling, dismantling, crown reduction, climbing operations and chipping, brings hazards a RAMS has to address:

  • falls from height during climbing and aerial rescue
  • chainsaw cuts and kickback
  • falling timber and branches striking people below
  • contact with overhead power lines
  • chipper entanglement and noise

Generate your RAMS in minutes

Built to the correct published standard for a tree surgeon: specific controls, the right legal basis, a review date and a sign-off section you can operate.

Start your RAMS

FAQ

Do tree surgeons & arborists legally need a RAMS?

A combined Risk Assessment & Method Statement, the site-ready document a principal contractor or client asks for before you start. For tree surgeon work, meaning felling, dismantling, crown reduction, climbing operations and chipping, it is the document a client, principal contractor or inspector expects to see, grounded in MHSWR 1999 reg 3 (HSE): the combined risk assessment + method statement contractors submit.

What must a tree surgeon's RAMS contain?

At minimum: A hazard table with a likelihood × severity score before and after controls; controls in the correct hierarchy (eliminate → substitute → engineering → admin → PPE last); A numbered, step-by-step method statement for the actual task; PPE to BS EN standards, emergency arrangements, and an operative sign-off.

Why does a tree surgeon's RAMS get rejected?

The usual reasons: residual risk dropped from high to low on PPE or 'competent operatives' alone; generic hazards that could apply to any job; no method statement, or one too vague to follow on site; the wrong legal basis cited, such as CDM 2015 named for work that is not construction.

Which regulation is a tree surgeon's RAMS written under?

MHSWR 1999. The full text is on legislation.gov.uk at https://www.legislation.gov.uk/uksi/1999/3242/contents.

How fast can I get a RAMS?

A couple of minutes. Describe the job, and RAMSReady writes a RAMS for your exact tree surgeon job live against the correct standard, with a review date and a sign-off/records section.

Not writing this one today?

We will email you a one page overview of what RAMSReady covers, so you have it when you need it.

Want to see how it would work for your firm?

Tell us roughly what you run and who keeps your records, and we will come back to you.

Related guides

Other documents for Tree Surgeons & Arborists

Similar trades

Templates and tools